XI-IATI-IADB-CR-L1139
Inter-American Development Bank
Road Infrastructure Program and promotion of Public-Private Partnerships (PPP)
Programa de Infraestructura Vial y promoción de Asociaciones Público-Privadas (APP)
To contribute to the country's competitiveness through the environmentally sustainable improvement of the High-capacity Road Network (RVAC) in the GMA and to support the development of road infrastructure projects through public-private partnerships (PPPs) as an additional mechanism for their financing and management. The specific objectives are to: (i) lower vehicle operating costs for the flow of freight transportation on the RVAC in the GMA; (ii) shorten travel times for vehicles on the RVAC in the GMA; (iii) minimize emissions generated by transportation in the GMA; and (iv) improve the technical and institutional capacity of the Government of Costa Rica to develop road projects via PPP mechanisms
Contribuir a la competitividad del país mediante la mejora y ampliación ambientalmente sostenible de la Red Vial de Alta Capacidad (RVAC) en el GAM, y apoyar el desarrollo de proyectos de infraestructura vial a través de modelos de Asociaciones Público-Privadas (APP) como mecanismo complementario para su financiamiento y gestión. Los objetivos específicos son: (i) disminuir los costos de operación vehicular del flujo de transporte de carga que circula por la RVAC en el GAM; (ii) disminuir tiempos de viaje de los vehículos que circulan por la RVAC en el GAM; (iii) minimizar las emisiones generadas por el transporte en el GAM; y (iv) mejorar la capacidad técnica e institucional del GdCR para desarrollar proyectos viales mediante esquemas de APP
INTER AMERICAN DEVELOPMENT BANK
Ordinary Capital
REPUBLICA DE COSTA RICA
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Diseño de Obras Urbanas Complementarias (OUC): Elaboración de tres diseños finales de: (i) parque metropolitano de Alajuela; (ii) parque lineal de Taras-La Lima; y (iii) circuito recreativo de occidente en San Ramón realizados (Fuente BID) Programa de Infraestructura Vial y promoción de Asociaciones Público-Privadas (APP), Costa Rica
nan
TRANSPORT
TRANSPORTE
1563750.0
1595000.0
1625000.0
1651250.0
1676250.0
1700000.0
1721250.0
1737500.0
1755000.0
1766250.0
1777500.0
1783750.0
1788750.0
1790000.0
1788750.0
1783750.0
1776250.0
1766250.0
1753750.0
1737500.0
1718750.0
1698750.0
1676250.0
1650000.0
1622500.0
1592500.0
1562500.0
1530000.0
1495000.0
1460000.0
1423750.0
1386250.0
1348750.0
1310000.0
1270000.0
1231250.0
1192500.0
1152500.0
1112500.0
1075000.0
1035000.0
997500.0
958750.0
922500.0
886250.0
850000.0
815000.0
781250.0
747500.0
716250.0
685000.0
653750.0
625000.0
596250.0
570000.0
542500.0
517500.0
492500.0
468750.0
446250.0
425000.0
403750.0
385000.0
365000.0
6067500.0
20000000
Disbursement in second quarter of 2021
51561.64
Interest repayment in third quarter of 2021
123326.03
Interest repayment in first quarter of 2022
249827.79
Interest repayment in third quarter of 2022
511489.7
Interest repayment in first quarter of 2023
10000000
Disbursement in third quarter of 2023
652205.7
Interest repayment in third quarter of 2023
10000000
Disbursement in forth quarter of 2023
1224844.3
Interest repayment in first quarter of 2024
CR-L1139_P710302_SP.pdf
EEO6 Resumen Ejecutivo Estudios y diseños del proyecto Taras – La Lima.pdf
EER2 Plan de Monitoreo y Evaluación.docx
CR-L1139 First period Jan-Jun 2020 - Public Report.pdf
EEO2 Manual de Operaciones (Borrador MANOP).docx
LP CR-L1139 (EN) (2).pdf
CR-L1139 First period Jan-Jun 2023 - Public Report.PDF
EEO8 Análisis de capacidad institucional del Fideicomiso Ruta 1 del BCR.docx
CR-L1139 Second period Jan-Dec 2021 - Public Report.PDF
EEO1 Análisis Económico del Proyecto.pdf
EEO17 Análisis de personas con discapacidad en Costa Rica.docx
EEO14 Decreto Ejecutivo 39240 de 2015. Funciones del CAS y su UE.pdf
EEO3 Evaluación del Programa CR-L1032 .pdf
EEO12 Plan Nacional de Desarrollo e Inversiones Públicas 2019-2022.pdf
CR-L1139_P612810_SP.pdf
EEO10 Plan de Descarbonizacion 2018-2050.pdf
CR-L1139 Second period Jan-Dec 2019-Public Report.pdf
CR-L1139 Second period Jan-Dec 2022 - Public Report.PDF
EEO5 Análisis del DOT en Costa Rica.docx
EEO11 Plan Nacional del Desarrollo Urbano 2018-2030.pdf
CR-L1139 Second period Jan-Dec 2020 - Public Report.pdf
Copy of EEO16 Plan Financiero a partir del PEP_POA.xlsx
EER4 Plan de Adquisiciones.xlsx
EER 1 Plan de Ejecución Plurianual (PEP)-Plan Operativo Anual (POA).pdf
CR-L1139 First period Jan-Jun 2022 - Public Report.PDF
EEO9 Análisis de Género.docx
CR-L1139 First period Jan-Jun 2021 - Public Report.pdf
CR-L1139_P2042240_SP.pdf
EEO13 Plan Nacional de Transporte 2011-2035.pdf
EEO4 Análisis de APP´s en Costa Rica.doc
EEO7 Resumen de Estudios y diseños de las OBIS San José – San Ramón.docx
EER3 Informe de Gestión Ambiental y Social (IGAS).docx
Desarrollo de capacidades institucionales
Desarrollo de capacidades institucionales
Diseño de Obras Urbanas Complementarias (OUC): Elaboración de tres diseños finales de: (i) parque metropolitano de Alajuela; (ii) parque lineal de Taras-La Lima; y (iii) circuito recreativo de occidente en San Ramón realizados (Fuente BID)
Diseño de Obras Urbanas Complementarias (OUC): Elaboración de tres diseños finales de: (i) parque metropolitano de Alajuela; (ii) parque lineal de Taras-La Lima; y (iii) circuito recreativo de occidente en San Ramón realizados (Fuente BID)
Infraestructura.
Infraestructura.
LOTE #1 Programa de OBIS en el corredor San Ramón – San José: Puentes e Intercambio construidos (Fuente Contrapartida).
LOTE #1 Programa de OBIS en el corredor San Ramón – San José: Puentes e Intercambio construidos (Fuente Contrapartida).
LOTE #2 Programa de OBIS en el corredor San Ramón – San José: Conector Barreal y rampas Castella construido (Fuente Contrapartida).
LOTE #2 Programa de OBIS en el corredor San Ramón – San José: Conector Barreal y rampas Castella construido (Fuente Contrapartida).
XI-IATI-IADB-CR0150
Inter-American Development Bank
Sustainable Development of the Binational Watershed Rio Sixaola
Desarrollo Sostenible de la Cuenca Binacional del Río Sixaola
Short, medium and long-term measures will be defined for improving the quality of life of the population in the basin and for attaining: (i) adequate equilibrium between natural resources conservation and the improvement and sustainability of the economic activities; (ii) orienting the public investment in infrastructure and basic services; and (iii) increase the capacity of the institutions responsible for the management of the natural resources with the effective participation of the communities and local governments.
Se definirán medidas a corto, mediano y largo plazo que permitan mejorar la calidad de vida de los habitantes de la cuenca que permitan: (i) garantizar un adecuado equilibrio entre la conservación de los recursos naturales y la mejora y sostenibilidad de las actividades productivas; (ii) orientar la inversión pública en infraestructura y servicios básicos; y (iii) aumentar la capacidad de las instituciones responsables de la administración de los recursos con la participación efectiva de las comunidades y los gobiernos locales.
Ordinary Capital
REPUBLICA DE COSTA RICA
INTER AMERICAN DEVELOPMENT BANK
MINISTERIO DE AGRICULTURA Y GANADERIA (MAG)
MINISTERIO DE AGRICULTURA Y GANADERIA (MAG)
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Adopción de sistemas agroforestales sembrados o rehabilitados Desarrollo Sostenible de la Cuenca Binacional del Río Sixaola, Costa Rica
9.5103, -82.62552
WATER AND SANITATION
AGUA Y SANEAMIENTO
300000
Disbursement in first quarter of 2009
1514.63
Interest repayment in third quarter of 2009
2106.08
Interest repayment in first quarter of 2010
1885.4
Interest repayment in third quarter of 2010
2085.04
Interest repayment in first quarter of 2011
1593.37
Interest repayment in third quarter of 2011
415000
Disbursement in forth quarter of 2011
1805.12
Interest repayment in first quarter of 2012
4981.12
Interest repayment in third quarter of 2012
200375.2
Disbursement in third quarter of 2012
925273
Disbursement in forth quarter of 2012
4517.99
Interest repayment in first quarter of 2013
35206.65
Loan repayment in first quarter of 2013
12816.46
Interest repayment in third quarter of 2013
72217.75
Loan repayment in third quarter of 2013
400000
Disbursement in third quarter of 2013
3962707.24
Disbursement in forth quarter of 2013
20094.34
Interest repayment in first quarter of 2014
253997.13
Loan repayment in first quarter of 2014
33999.22
Interest repayment in third quarter of 2014
253997.13
Loan repayment in third quarter of 2014
3016644.56
Disbursement in forth quarter of 2014
37227.26
Interest repayment in first quarter of 2015
391117.33
Loan repayment in first quarter of 2015
48135.4
Interest repayment in third quarter of 2015
391117.33
Loan repayment in third quarter of 2015
63246.47
Interest repayment in first quarter of 2016
391117.33
Loan repayment in first quarter of 2016
71858.85
Interest repayment in third quarter of 2016
390441.28
Loan repayment in third quarter of 2016
74634.53
Interest repayment in first quarter of 2017
390441.28
Loan repayment in first quarter of 2017
66577.62
Interest repayment in third quarter of 2017
390421.28
Loan repayment in third quarter of 2017
20
Loan repayment in third quarter of 2017
74245.5
Interest repayment in first quarter of 2018
390441.28
Loan repayment in first quarter of 2018
93549.09
Interest repayment in third quarter of 2018
390441.28
Loan repayment in third quarter of 2018
93616.49
Interest repayment in first quarter of 2019
390421.27
Loan repayment in first quarter of 2019
20.01
Loan repayment in second quarter of 2019
92735.83
Interest repayment in third quarter of 2019
390441.28
Loan repayment in third quarter of 2019
68682.63
Interest repayment in first quarter of 2020
390441.28
Loan repayment in first quarter of 2020
46705.84
Interest repayment in third quarter of 2020
390441.28
Loan repayment in third quarter of 2020
16337.91
Interest repayment in first quarter of 2021
390441.28
Loan repayment in first quarter of 2021
1574.54
Interest repayment in second quarter of 2021
20831.01
Interest repayment in third quarter of 2021
390441.28
Loan repayment in third quarter of 2021
18659.88
Interest repayment in first quarter of 2022
390441.28
Loan repayment in first quarter of 2022
26861.3
Interest repayment in third quarter of 2022
390441.28
Loan repayment in third quarter of 2022
63354.01
Interest repayment in first quarter of 2023
390441.28
Loan repayment in first quarter of 2023
60640.41
Interest repayment in third quarter of 2023
390441.28
Loan repayment in third quarter of 2023
53349.74
Interest repayment in first quarter of 2024
390441.28
Loan repayment in first quarter of 2024
Informe para Publicación_PMR-_CR0150-2012-1º-Periodo [37353348].PDF
Report for Publication_PMR-_CR0150-2011-2º-Period [37298344].PDF
Informe para Publicación_PMR-_CR0150-2011-1º-Periodo [36625067].PDF
Rapport pour Publication_PMR-_CR0150-2010-2º-Período [36312061].PDF
Rapport pour Publication_PMR-_CR0150-2011-1º-Período [36624513].PDF
CR0150 First period Jan-Jun 2015-Public Report [40181910].PDF
Programa de Desarrollo Sostenible de la Cuenca Binacional del Río Sixaola [320207].DOC
Report for Publication_PMR-_CR0150-2011-1º-Period [36625630].PDF
Report for Publication_PMR-_CR0150-2013-1º-Period [38267356].PDF
Report for Publication_PMR-_CR0150-2010-2º-Period [36313221].PDF
Informe para Publicación_PMR-_CR0150-2012-2º-Periodo [37874464].PDF
Relatório para publicação_PMR-_CR0150-2013-1º-Período [38265361].PDF
Informe para Publicación_PMR-_CR0150-2010-2º-Periodo [36312647].PDF
CR0150 First period Jan-Jun 2014-Public Report [40176163].PDF
Programa de Desarrollo Sostenible de la Cuenca Binacional del Río Sixaola [319433].DOC
CR0150 Second period Jan-Dec 2015-Public Report [40363566].PDF
PROGRAMA DE DESARROLLO SOSTENIBLE DE LA CUENCA BINACIONAL DE [35238297].PDF
Rapport pour Publication_PMR-_CR0150-2013-1º-Período [38266018].PDF
Relatório para publicação_PMR-_CR0150-2011-2º-Período [37297768].PDF
CR0150 First period Jan-Jun 2016-Public Report [40797351].PDF
Report for Publication_PMR-_CR0150-2012-2º-Period [37875248].PDF
CR0150 Second period Jan-Dec 2014-Public Report [40178716].PDF
Rapport pour Publication_PMR-_CR0150-2012-2º-Período [37873810].PDF
Relatório para publicação_PMR-_CR0150-2011-1º-Período [36623929].PDF
CR0150 Second period Jan-Dec 2013-Public Report [40173242].PDF
Rapport pour Publication_PMR-_CR0150-2012-1º-Período [37352680].PDF
Informe para Publicación_PMR-_CR0150-2013-1º-Periodo [38266681].PDF
Relatório para publicação_PMR-_CR0150-2012-1º-Período [37352029].PDF
Informe para Publicación_PMR-_CR0150-2011-2º-Periodo [37298151].PDF
Programa de Desarrollo Sostenible de la Cuenca Binacional del Río Sixaola [319970].DOC
Report for Publication_PMR-_CR0150-2012-1º-Period [37354006].PDF
Relatório para publicação_PMR-_CR0150-2012-2º-Período [37873142].PDF
Sustainable Development Program for the Sixaola River Binational Watershed [407842].PDF
Rapport pour Publication_PMR-_CR0150-2011-2º-Período [37297959].PDF
Relatório para publicação_PMR-_CR0150-2010-2º-Período [36310167].PDF
1. Gestión Ambiental, Manejo de los Recursos Naturales y Reducción de la Vulnerabilidad
1. Gestión Ambiental, Manejo de los Recursos Naturales y Reducción de la Vulnerabilidad
Proyecto piloto de participación comunitaria implementado
Proyecto piloto de participación comunitaria implementado
Proyecto de manejo de residuos sólidos implementado
Proyecto de manejo de residuos sólidos implementado
Planta de Biodiesel construida
Planta de Biodiesel construida
Sendero Turistico del Refugio de Vida Silvestre Gandoca Manzanillo construido
Sendero Turistico del Refugio de Vida Silvestre Gandoca Manzanillo construido
Información topográfica del Rio Sixaola documentada.
Información topográfica del Rio Sixaola documentada.
Proyecto piloto de participación comunitaria implementado
Proyecto piloto de participación comunitaria implementado
Plan de Reducción de la Vulnerabilidad Cuenca Baja del Río Sixaola implementado
Plan de Reducción de la Vulnerabilidad Cuenca Baja del Río Sixaola implementado
2. Diversificación Productiva.
2. Diversificación Productiva.
Proyectos de fortalecimiento de redes de ecoturismo rural comunitario ejecutados
Proyectos de fortalecimiento de redes de ecoturismo rural comunitario ejecutados
Laboratorio para mejora de producción agrícola construido
Laboratorio para mejora de producción agrícola construido
Proyectos agroindustriales para el apoyo a la diversificación productiva implementados
Proyectos agroindustriales para el apoyo a la diversificación productiva implementados
Productores capacitados en diversificación productiva y ambientalmente sostenible.
Productores capacitados en diversificación productiva y ambientalmente sostenible.
Proyecto de mejora a la producción pecuaria indígena implementado
Proyecto de mejora a la producción pecuaria indígena implementado
Adopción de sistemas agroforestales sembrados o rehabilitados
Adopción de sistemas agroforestales sembrados o rehabilitados
Productores capacitados en diversificación productiva y ambientalmente sostenible.
Productores capacitados en diversificación productiva y ambientalmente sostenible.
3- Servicos públicos e infraestructura básica.
3- Servicos públicos e infraestructura básica.
Diseños de acueductos elaborados
Diseños de acueductos elaborados
Tubería de drenaje construida
Tubería de drenaje construida
Puentes construidos
Puentes construidos
Diseños de puentes elaborados
Diseños de puentes elaborados
4- Fortalecimiento de la Capacidad de Gestión.
4- Fortalecimiento de la Capacidad de Gestión.
Comite Distrital en la cuenca del rio sixaola creado y operando
Comite Distrital en la cuenca del rio sixaola creado y operando
Sistema de información de Talamanca implementado
Sistema de información de Talamanca implementado
Organizaciones locales fortalecidas en su gestión y desarrollo comunal
Organizaciones locales fortalecidas en su gestión y desarrollo comunal
XI-IATI-IADB-CR-L1032
Inter-American Development Bank
Infrastructure Transport Program (PIT)
Programa de Infraestructura de Transporte (PIT)
Contribute to the development of the transport sector through the improvment of road and port infrastructure, which will benefit the conditions of mobility of people and goods, facilitating the flow of trade and regional economic integration of Costa Rica.
Contribuir al desarrollo del sector transporte a través de la mejora de la infraestructura vial y portuaria, lo que beneficiará las condiciones de movilidad de las personas y los bienes, facilitando el flujo de comercio y la integración económica regional de Costa Rica.
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
REPUBLICA DE COSTA RICA
China Co Financing Fund for Latin America and the Caribbean
REPUBLICA DE COSTA RICA
Ordinary Capital
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Diseño de Intercambiadores La Lima y Taras. Ruta 2. Km de la red vial primaria mejorados y ampliados a cuatro carriles. Programa de Infraestructura de Transporte (PIT), Costa Rica
24.58476, -107.38093
TRANSPORT
TRANSPORTE
5382000.0
5256000.0
5125500.0
4990500.0
4855500.0
4716000.0
4572000.0
4432500.0
4293000.0
4149000.0
4005000.0
3870000.0
3726000.0
3591000.0
3451500.0
3321000.0
3190500.0
3060000.0
2934000.0
2812500.0
2691000.0
2578500.0
2466000.0
2353500.0
2250000.0
2146500.0
2052000.0
1953000.0
1863000.0
1773000.0
1687500.0
1606500.0
1530000.0
1453500.0
1386000.0
1314000.0
24162500.0
5000000
Disbursement in second quarter of 2016
49285.52
Interest repayment in forth quarter of 2016
51574.73
Interest repayment in second quarter of 2017
5000000
Disbursement in second quarter of 2017
87865.75
Interest repayment in forth quarter of 2017
40000000
Disbursement in forth quarter of 2017
463380.83
Interest repayment in second quarter of 2018
826232.88
Interest repayment in forth quarter of 2018
120000000
Disbursement in forth quarter of 2018
2529486.84
Interest repayment in second quarter of 2019
2845028.22
Interest repayment in forth quarter of 2019
2385407.71
Interest repayment in second quarter of 2020
1284150.27
Interest repayment in forth quarter of 2020
15000000
Disbursement in forth quarter of 2020
30000000
Disbursement in first quarter of 2021
62019.5
Interest repayment in second quarter of 2021
1028024.2
Interest repayment in second quarter of 2021
5000000
Loan repayment in second quarter of 2021
5000000
Disbursement in second quarter of 2021
117682.2
Interest repayment in forth quarter of 2021
1033868.09
Loan repayment in forth quarter of 2021
1217778.08
Interest repayment in forth quarter of 2021
5909090.91
Loan repayment in forth quarter of 2021
40000000
Disbursement in first quarter of 2022
119438.2
Interest repayment in second quarter of 2022
592691.62
Loan repayment in second quarter of 2022
1307347.2
Interest repayment in second quarter of 2022
7159090.91
Loan repayment in second quarter of 2022
10000000
Disbursement in third quarter of 2022
40000000
Disbursement in third quarter of 2022
312523.97
Interest repayment in forth quarter of 2022
915272.27
Loan repayment in forth quarter of 2022
3405071.07
Interest repayment in forth quarter of 2022
8449413.49
Loan repayment in forth quarter of 2022
766172.34
Interest repayment in second quarter of 2023
915272.27
Loan repayment in second quarter of 2023
7073097.37
Interest repayment in second quarter of 2023
8449413.49
Loan repayment in second quarter of 2023
3000000
Disbursement in third quarter of 2023
869808.81
Interest repayment in forth quarter of 2023
915272.27
Loan repayment in forth quarter of 2023
8054251.2
Interest repayment in forth quarter of 2023
8449413.49
Loan repayment in forth quarter of 2023
Enlace Electrónico Requerido _7_ Plan de Ejecución del Programa [37908482].XLSX
CR-L1032 Second period Jan-Dec 2020 - Public Report.pdf
CR-L1032 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1032_P573211_SP.pdf
Enlace Electrónico Opcional _1_ Mapa de localización de proyectos PIT [37901960].JPG
Enlace Electrónico Opcional _4_ Evaluación económica Terminales Transbordadoras [37908834].docx
CR-L1032_P859970_SP.pdf
CR-L1032 First period Jan-Jun 2014-Public Report [40176162].PDF
CR-L1032 First period Jan-Jun 2023 - Public Report.PDF
CR-L1032 Second period Jan-Dec 2019-Public Report.pdf
CR-L1032 Second period Jan-Dec 2017-Public Report.pdf
CR-L1032 First period Jan-Jun 2020 - Public Report.pdf
CR-L1032 Second period Jan-Dec 2018-Public Report.pdf
CR-L1032 Programa de Infraestructura de Transporte -PIT_ IGAS 2013-07-15 [37546213].docx
CR-L1032_7283_1_SP.pdf
CR-L1032 [40681614].PDF
CR-L1032_P906193_SP.pdf
Enlace Electrónico Opcional _5-B_ Ficha Técnica - Proyecto Mejoramiento Terminales Transboradores Golfo Nicoya [37908243].DOC
CR-L1032 Second period Jan-Dec 2015-Public Report [40363577].PDF
CR-L1032 First period Jan-Jun 2019-Public Report.pdf
CR-L1032 First period Jan-Jun 2022 - Public Report.PDF
Costa Rica_ Programa de Infraestructura de Transporte (PIT) [38203759].PDF
Enlace Electrónico Opcional _8_ Estudio sobrecostos [37907204].PDF
CR-L1032_P518919_SP.pdf
Enlace Electrónico Opcional _5-A_ Ficha Técnica del Rompeolas Puerto Caldera [37908146].DOC
Costa Rica_ Transportation Infrastructure Program (PIT) [38203765].PDF
CR-L1032 [40682549].PDF
CR-L1032 First period Jan-Jun 2015-Public Report [40181891].PDF
CR-L1032 [39356072].PDF
CR-L1032 First period Jan-Jun 2018-Public Report.pdf
Enlace Electrónico Opcional _11_ Sector portuario de Costa Rica - Esquema de gestión [38066016].docx
Enlace Electrónico Opcional _10_ Informe de Evaluación de la Red Vial Nacional Pavimentada de Costa Rica 2012-20 [37902006].PDF
CR-L1032 [40374172].PDF
Enlace Electrónico Requerido _2_ Plan de Adquisiciones_POD [37899872].XLSX
Contrato Modificatorio No 1 - Programa de Infraestructura de Transporte. PIT.pdf
CR-L1032 First period Jan-Jun 2017-Public Report.pdf
CR-L1032_8918_2_SP.pdf
CR-L1032 1485.pdf
CR-L1032_P647283_SP.pdf
CR-L1032 Second period Jan-Dec 2013-Public Report [40173256].PDF
Enlace Electrónico Requerido _3_ Plan Operativo Anual [37908525].PDF
CR-L1032 Second period Jan-Dec 2014-Public Report [40178688].PDF
CR-L1032 First period Jan-Jun 2021 - Public Report.pdf
CR-L1032 Second period Jan-Dec 2021 - Public Report.PDF
CR-L1032 First period Jan-Jun 2016-Public Report [40797361].PDF
CR-L1032 [40316857].PDF
Enlace Electrónico Opcional _6_ Estudio factibilidad Técnica y Financiera de la vía Limonal - Barranca [37908466].PDF
CR-L1032 Second period Jan-Dec 2016-Public Report.pdf
Obras marítimo-portuarias
Obras marítimo-portuarias
Plan Maestro Caldera desarrollado
Plan Maestro Caldera desarrollado
Obras viales
Obras viales
Diseño de Intercambiadores La Lima y Taras. Ruta 2. Km de la red vial primaria mejorados y ampliados a cuatro carriles.
Diseño de Intercambiadores La Lima y Taras. Ruta 2. Km de la red vial primaria mejorados y ampliados a cuatro carriles.
XI-IATI-IADB-CR-L1031
Inter-American Development Bank
Violence Prevention and Social Inclusion Promotion Program
Programa para la Prevención de la Violencia y Promoción de la Inclusión Social
The program objective is to contribute in preventing violence and crime in the areas of intervention. The specific objectives of the program will strengthen management skills and MJP action to implement interventions in two main areas: (i) secondary prevention of violence at national and local level and (ii) rehabilitation and reintegration of the population in conflict with the law through tertiary prevention programs for violence.
El objetivo general del Programa será contribuir a la prevención de la violencia y el delito en las áreas de intervención. El objetivo específico del Programa será fortalecer las capacidades de gestión y acción del MJP para ejecutar intervenciones en sus dos principales áreas de actuación: (i) prevención secundaria de la violencia a nivel nacional y local y (ii) rehabilitación y reinserción de la población en conflicto con la ley penal, a través de programas de prevención terciaria de la violencia.
Ordinary Capital
REPUBLICA DE COSTA RICA
MINISTERIO DE JUSTICIA Y PAZ
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Centros Cívicos por la Paz funcionando (incluyendo las actividades de escuela de música, arte, deporte y resolución alterna de conflictos de Casas de Justicia) Programa para la Prevención de la Violencia y Promoción de la Inclusión Social, Costa Rica
nan
SOCIAL INVESTMENT
INVERSIONES SOCIALES
1820974
Disbursement in forth quarter of 2012
1820974
Disbursement in forth quarter of 2012
3000
Disbursement in first quarter of 2013
5756.15
Interest repayment in first quarter of 2013
10761.83
Interest repayment in third quarter of 2013
10000000
Disbursement in forth quarter of 2013
43047.72
Interest repayment in second quarter of 2014
68271.3
Interest repayment in third quarter of 2014
30106798.94
Disbursement in forth quarter of 2014
170289.13
Interest repayment in first quarter of 2015
250355.44
Interest repayment in third quarter of 2015
381598.97
Interest repayment in first quarter of 2016
15000000
Disbursement in second quarter of 2016
515782.75
Interest repayment in third quarter of 2016
45000000
Disbursement in forth quarter of 2016
1003564.7
Interest repayment in first quarter of 2017
12000000
Disbursement in second quarter of 2017
1181944.15
Interest repayment in third quarter of 2017
2998178.24
Loan repayment in third quarter of 2017
18510337.06
Disbursement in forth quarter of 2017
1544047.73
Interest repayment in first quarter of 2018
3498457.62
Loan repayment in first quarter of 2018
2066270.53
Interest repayment in third quarter of 2018
3498457.62
Loan repayment in third quarter of 2018
2180432.41
Interest repayment in first quarter of 2019
3498437.62
Loan repayment in first quarter of 2019
20
Loan repayment in second quarter of 2019
2030740.65
Interest repayment in third quarter of 2019
3498457.62
Loan repayment in third quarter of 2019
1635842.39
Interest repayment in first quarter of 2020
3498457.62
Loan repayment in first quarter of 2020
930830.6
Interest repayment in third quarter of 2020
3498457.62
Loan repayment in third quarter of 2020
645113.85
Interest repayment in first quarter of 2021
3498457.62
Loan repayment in first quarter of 2021
637825.37
Interest repayment in third quarter of 2021
3498457.62
Loan repayment in third quarter of 2021
630045.38
Interest repayment in first quarter of 2022
3498457.62
Loan repayment in first quarter of 2022
1402158.8
Interest repayment in third quarter of 2022
3498457.62
Loan repayment in third quarter of 2022
2511921
Interest repayment in first quarter of 2023
3498457.62
Loan repayment in first quarter of 2023
2964784.68
Interest repayment in third quarter of 2023
3498457.62
Loan repayment in third quarter of 2023
Informe para Publicación_PMR-_CR-L1031-2011-1º-Periodo [36625064].PDF
CR-L1031 [40200149].PDF
CR-L1031 Second period Jan-Dec 2013-Public Report [40173274].PDF
Rapport pour Publication_PMR-_CR-L1031-2013-1º-Período [38266011].PDF
Report for Publication_PMR-_CR-L1031-2011-2º-Period [36927249].PDF
CR-L1031 [38850074].PDF
Relatório para publicação_PMR-_CR-L1031-2011-2º-Período [36915796].PDF
Rapport pour Publication_PMR-_CR-L1031-2012-2º-Período [37873804].PDF
Report for Publication_PMR-_CR-L1031-2011-1º-Period [36625627].PDF
Relatório para publicação_PMR-_CR-L1031-2011-1º-Período [36623924].PDF
CR-L1031 Second period Jan-Dec 2016-Public Report.pdf
CR-L1031 [39892093].PDF
Rapport pour Publication_PMR-_CR-L1031-2011-1º-Período [36624510].PDF
CR-L1031 [39992804].PDF
CR-L1031 [40755038].PDF
CR-L1031 [38850067].PDF
CR-L1031 [39985633].PDF
CR-L1031 [39992771].PDF
CR-L1031 [39999868].PDF
Violence Prevention and Social Inclusion Promotion Program - Loan Proposal [36218685].PDF
Programa para la Prevención de la Violencia y la Inclusión Social - Plan de Adquisiciones [36218707].PDF
CR-L1031 First period Jan-Jun 2018-Public Report.pdf
Versión Final del Informe de Seguimiento de Proyecto (PMR) y Cambios a la Matriz de Resultados.pdf
Report for Publication_PMR-_CR-L1031-2013-1º-Period [38267348].PDF
CR-L1031 First period Jan-Jun 2017-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1031-2011-2º-Período [36922010].PDF
CR-L1031 [39999869].PDF
CR-L1031 First period Jan-Jun 2016-Public Report [40797360].PDF
CR-L1031 Second period Jan-Dec 2015-Public Report [40363576].PDF
CR-L1031 [40814695].PDF
Programa para la Prevención de la Violencia y la Promoción de la Inclusión Social - Propuesta de Préstamo [36218674].PDF
CR-L1031 [39654111].PDF
CR-L1031 [39414590].PDF
CR-L1031 [39892094].PDF
Informe para Publicación_PMR-_CR-L1031-2012-1º-Periodo [37353343].PDF
CR-L1031 [38850068].PDF
Relatório para publicação_PMR-_CR-L1031-2012-1º-Período [37352023].PDF
Relatório para publicação_PMR-_CR-L1031-2012-2º-Período [37873136].PDF
Informe para Publicación_PMR-_CR-L1031-2011-2º-Periodo [36924598].PDF
CR-L1031 Second period Jan-Dec 2014-Public Report [40178704].PDF
CR-L1031 [39654109].PDF
CR-L1031 [38850876].PDF
Violence Prevention and Social Inclusion Promotion Program - Procurement Plan [36218715].PDF
Report for Publication_PMR-_CR-L1031-2012-1º-Period [37354001].PDF
Contrato - Programa para la Prevención de la Violencia y Promoción de la Inclusión Social.pdf
CR-L1031 [39966596].PDF
CR-L1031 [39999860].PDF
CR-L1031 First period Jan-Jun 2014-Public Report [40176138].PDF
CR-L1031 [40084529].PDF
CR-L1031 Second period Jan-Dec 2018-Public Report.pdf
CR-L1031 [38991328].PDF
CR-L1031 First period Jan-Jun 2015-Public Report [40181906].PDF
Rapport pour Publication_PMR-_CR-L1031-2012-1º-Período [37352675].PDF
CR-L1031 Second period Jan-Dec 2017-Public Report.pdf
CR-L1031 [40767840].PDF
CR-L1031 [39985639].PDF
CR-L1031 [39763710].PDF
Anexo I Resumen DEM.pdf
Informe para Publicación_PMR-_CR-L1031-2013-1º-Periodo [38266674].PDF
Componente 1. Fortalecimiento de capacidad institucional del Ministerio de Seguridad y Ministerio de Justicia y Paz
Componente 1. Fortalecimiento de capacidad institucional del Ministerio de Seguridad y Ministerio de Justicia y Paz
Modelo de Transparencia del MJP y del MSP implementado
Modelo de Transparencia del MJP y del MSP implementado
Componente 2. Acciones de prevención del delito violento a nivel local
Componente 2. Acciones de prevención del delito violento a nivel local
Centros Cívicos por la Paz funcionando (incluyendo las actividades de escuela de música, arte, deporte y resolución alterna de conflictos de Casas de Justicia)
Centros Cívicos por la Paz funcionando (incluyendo las actividades de escuela de música, arte, deporte y resolución alterna de conflictos de Casas de Justicia)
Centros Cívicos por la Paz funcionando (incluyendo las actividades de escuela de música, arte, deporte y resolución alterna de conflictos de Casas de Justicia)
Centros Cívicos por la Paz funcionando (incluyendo las actividades de escuela de música, arte, deporte y resolución alterna de conflictos de Casas de Justicia)
XI-IATI-IADB-CR-L1053
Inter-American Development Bank
Building and Equipping of Education Infraestructure
Construcción y Equipamiento de Infraestructura Educativa
The general objective of the program is to improve the physical conditions of education infrastructure, the learning environments, and the internal efficiency of beneficiary primary and secondary schools by providing infrastructure to schools that currently lack it. To this end, direct financing will be provided to build and equip school infrastructure through a public works development trust. The specific objectives are: (i) to promote the gradual consolidation of a high-quality physical and technological platform to support the transformation of the teaching/learning process; (ii) to reduce the education infrastructure deficit; and (iii) to implement an alternative financing mechanism to address the demand for education infrastructure in a more flexible and timely manner, through long-term financing instruments.
El Proyecto tiene como objetivo general mejorar las condiciones físicas de la infraestructura escolar, los ambientes de aprendizaje y la eficiencia interna de las escuelas y colegios beneficiarios mediante la dotación de infraestructura propia a establecimientos que hoy día no cuentan con la misma. Como objetivos específicos, se espera: (i) impulsar la consolidación gradual de una plataforma física y tecnológica de calidad para apoyar la transformación del proceso de enseñanza-aprendizaje; (ii) reducir el déficit de infraestructura educativa que enfrenta el sistema educativo costarricense; y (iii) implementar un mecanismo de financiamiento alternativo para la atención de la demanda por infraestructura educativa de una manera más ágil y oportuna mediante instrumentos de financiamiento de largo plazo.
INTER AMERICAN DEVELOPMENT BANK
BANCO NACIONAL DE COSTA RICA
BANCO NACIONAL DE COSTA RICA
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Colegios de secundaria construidos y equipados Construcción y Equipamiento de Infraestructura Educativa, Costa Rica
24.58476, -107.38093
EDUCATION
EDUCACION
130000
Disbursement in third quarter of 2014
15000000
Disbursement in forth quarter of 2014
614.29
Interest repayment in first quarter of 2015
101570.51
Interest repayment in third quarter of 2015
116746.05
Interest repayment in first quarter of 2016
141093.58
Interest repayment in third quarter of 2016
10754103.22
Disbursement in forth quarter of 2016
156124.97
Interest repayment in first quarter of 2017
280274.76
Interest repayment in third quarter of 2017
35000000
Disbursement in forth quarter of 2017
301191.68
Interest repayment in first quarter of 2018
986374.5
Interest repayment in third quarter of 2018
15000000
Disbursement in third quarter of 2018
91640130.78
Disbursement in forth quarter of 2018
1732729.33
Interest repayment in first quarter of 2019
2985763.76
Interest repayment in third quarter of 2019
1096886.3
Loan repayment in third quarter of 2019
2778950.38
Interest repayment in first quarter of 2020
4489852
Loan repayment in first quarter of 2020
2667023.35
Interest repayment in third quarter of 2020
6023136.7
Loan repayment in third quarter of 2020
2596830.71
Interest repayment in first quarter of 2021
6032892.6
Loan repayment in first quarter of 2021
2541556.86
Interest repayment in third quarter of 2021
6032892.6
Loan repayment in third quarter of 2021
4381069.74
Interest repayment in third quarter of 2021
6032892.6
Loan repayment in third quarter of 2021
702043.98
Interest repayment in forth quarter of 2021
6032932.59
Loan repayment in forth quarter of 2021
2293756.95
Interest repayment in first quarter of 2022
5304517.56
Loan repayment in first quarter of 2022
2063907.86
Interest repayment in third quarter of 2022
5304557.55
Loan repayment in third quarter of 2022
2007858.45
Interest repayment in first quarter of 2023
5304557.55
Loan repayment in first quarter of 2023
1854019.01
Interest repayment in third quarter of 2023
5304557.55
Loan repayment in third quarter of 2023
1797233.69
Interest repayment in first quarter of 2024
5304557.55
Loan repayment in first quarter of 2024
CR-L1053 First period Jan-Jun 2019-Public Report.pdf
Contrato - Construcción y Equipamiento de Infraestructura Educativa [39083940].PDF
CR-L1053 Second period Jan-Dec 2016-Public Report.pdf
CR-L1053 [40854053].PDF
CR-L1053 Second period Jan-Dec 2018-Public Report.pdf
CR-L1053 Second period Jan-Dec 2019-Public Report.pdf
CR-L1053 First period Jan-Jun 2021 - Public Report.pdf
CR-L1053 Second period Jan-Dec 2020 - Public Report.pdf
PCR CR-L1053.pdf
CR-L1053 Second period Jan-Dec 2017-Public Report.pdf
CR-L1053 First period Jan-Jun 2018-Public Report.pdf
Contrato de Garantía - Construcción y Equipamiento de Infraestructura Educativa [39083640].PDF
CR-L1053 First period Jan-Jun 2020 - Public Report.pdf
CR-T1092 [40791130].PDF
CR-L1053 First period Jan-Jun 2017-Public Report.pdf
Construc y equipam esc primarias, esc educ especial e inst de enseñanza general
Construc y equipam esc primarias, esc educ especial e inst de enseñanza general
Número de unidades pedagógicas (educación general básica completa, 1 a 9) construidas y equipadas
Número de unidades pedagógicas (educación general básica completa, 1 a 9) construidas y equipadas
Número de escuelas de primaria construidas y equipadas.
Número de escuelas de primaria construidas y equipadas.
Construcción y equipamiento de colegios de secundaria en áreas rurales y urbano marginales
Construcción y equipamiento de colegios de secundaria en áreas rurales y urbano marginales
Liceos rurales que reemplazan centros de telesecundaria construidos y equipados
Liceos rurales que reemplazan centros de telesecundaria construidos y equipados
Terrenos comprados para la construcción de obras
Terrenos comprados para la construcción de obras
Colegios de secundaria construidos y equipados
Colegios de secundaria construidos y equipados
Colegios técnicos profesionales construidos y equipados.
Colegios técnicos profesionales construidos y equipados.
XI-IATI-IADB-CR-L1070
Inter-American Development Bank
First Renewable Energy, Transmission and Distribution of Electricity Program
Primer Programa de Energía Renovable, Transmisión y Distribución de Electricidad
The general objective of the conditional credit line for investment projects (CCLIP) is to contribute to the mitigation of climate change effects, to sustainable economic growth, and to promotion of regional integration through the Regional Electricity Market. The specific objective of the first loan under the CCLIP is to increase the supply of electricity based on renewable energies, through construction of the Las Pailas II and Borinquen I geothermal power plants and other additional electrical infrastructure.
El objetivo general de la Línea de Crédito Condicional para Proyectos de Inversión (CCLIP) es contribuir a la mitigación de los impactos del cambio climático, al crecimiento económico sostenible y al fomento de la integración regional mediante el Mercado Eléctrico Regional (MER). El objetivo específico del Primer Préstamo de la CCLIP es aumentar el suministro de electricidad con base en energías renovables, mediante la construcción de las plantas de generación de energía geotérmica Las Pailas II y Borinquen I y otras infraestructuras eléctricas adicionales.
Ordinary Capital
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Infraestructura de Transmisión Eléctrica Liberia-Papagayo-Nuevo Colón adquirida Primer Programa de Energía Renovable, Transmisión y Distribución de Electricidad, Costa Rica
24.58476, -107.38093
ENERGY
ENERGIA
2862000.0
2864000.0
2862000.0
2854000.0
2842000.0
2826000.0
2806000.0
2780000.0
2750000.0
2718000.0
2682000.0
2640000.0
2596000.0
2548000.0
2500000.0
2448000.0
2392000.0
2336000.0
2278000.0
2218000.0
2158000.0
2096000.0
2032000.0
1970000.0
1908000.0
1844000.0
1780000.0
1720000.0
1656000.0
1596000.0
1534000.0
1476000.0
1418000.0
1360000.0
1304000.0
1250000.0
1196000.0
1146000.0
1096000.0
1046000.0
1000000.0
954000.0
912000.0
868000.0
828000.0
788000.0
750000.0
714000.0
680000.0
646000.0
616000.0
584000.0
11708543.16
12142197.9
Disbursement in second quarter of 2019
23735632.11
Disbursement in third quarter of 2019
2375007.45
Disbursement in forth quarter of 2019
6232865.82
Disbursement in forth quarter of 2019
437114.24
Interest repayment in first quarter of 2020
544589.32
Interest repayment in third quarter of 2020
4077753.56
Disbursement in forth quarter of 2020
245277.58
Interest repayment in first quarter of 2021
304047.16
Interest repayment in third quarter of 2021
5000000
Disbursement in forth quarter of 2021
299411.92
Interest repayment in first quarter of 2022
438700.64
Interest repayment in third quarter of 2022
3000000
Disbursement in third quarter of 2022
2877859.51
Interest repayment in first quarter of 2023
816733.36
Interest repayment in first quarter of 2023
25000000
Disbursement in second quarter of 2023
92565.4
Interest repayment in third quarter of 2023
1948986.23
Interest repayment in third quarter of 2023
13000000
Disbursement in forth quarter of 2023
1962710.56
Interest repayment in first quarter of 2024
1209780.23
Interest repayment in first quarter of 2024
Plan de Seguimiento y Evaluación [39666734].docx
Estudio de Impacto Ambiental y Social Complementario Proyectos Geotérmicos Borinquen I y II [39800942].PDF
CR-L1070_P859964_SP.pdf
CR-L1070_P526895_SP.pdf
Evaluacion Ambiental Estrategica Guanacaste Proyecto Geotermico [39709291].PDF
CR-L1070 Second period Jan-Dec 2018-Public Report.pdf
CR-L1070_P975052_SP.pdf
CR-L1070 Second period Jan-Dec 2015-Public Report [40363591].PDF
CR-L1070_P782026_SP.pdf
CR-L1070-CCLIP - Costo y Financiamiento detallado [39854720].PDF
CR-L1070 First period Jan-Jun 2023 - Public Report.PDF
CR-L1070_P972349_SP.pdf
CR-L1070 Second period Jan-Dec 2017-Public Report.pdf
CR-L1070_6895_2_SP.pdf
Las Pailas II - Estudio de Impacto Ambieltal y Documentos Relacionados - Costa Rica [39506230].PDF
CR-L1070 Second period Jan-Dec 2021 - Public Report.PDF
Contrato Modificatorio No 1 - Primer Programa de Energía Renovable, Transmisión y Distribución de Electricidad.pdf
CR-L1070 First period Jan-Jun 2021 - Public Report.pdf
CR-L1070 First period Jan-Jun 2018-Public Report.pdf
CR-L1070_P832367_SP.pdf
CR-L1070 Second period Jan-Dec 2019-Public Report.pdf
CR-L1070_P828941_SP.pdf
CR-L1070_P975018_SP.pdf
Contrato - Primer Programa de Energía Renovable, Transmisión y Distribución de Electricidad.pdf
CR-L1070_P1042008_SP.pdf
CR-L1070 First period Jan-Jun 2020 - Public Report.pdf
CR-L1070_P982427_SP.pdf
CR-L1070 First period Jan-Jun 2016-Public Report [40797366].PDF
CR-L1070 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1070_P2065042_SP.pdf
CR-L1070_P964903_SP.pdf
CR-L1070_P900421_SP.pdf
CR-L1070_P1012191_SP.pdf
Evaluación de Efectos Acumulativos de los Proyectos Geotérmicos Las Pailas II y Borinquen I y II [39800913].PDF
Informe FINAL Gobierno Corporativo ICE - Objetivo 1- [39800101].PDF
CR-L1070 First period Jan-Jun 2017-Public Report.pdf
CR-L1070 First period Jan-Jun 2019-Public Report.pdf
CR-L1070 Second period Jan-Dec 2016-Public Report.pdf
CR-L1070_P884999_SP.pdf
CR-L1070_P2044715_SP.pdf
Plan de Accion de Biodiversidad Proyecto Geotermico Borinquen I y II [39709342].PDF
CR-L1070_P839822_SP.pdf
CR-L1070 Second period Jan-Dec 2020 - Public Report.pdf
CR-L1070_P880484_SP.pdf
CR-L1070 First period Jan-Jun 2022 - Public Report.PDF
CR-L1070_P1090773_SP.pdf
CR-L1070_P976764_SP.pdf
Subprograma I. Proyectos Geotérmicos Las Pailas II / Borinquen I
Subprograma I. Proyectos Geotérmicos Las Pailas II / Borinquen I
Terrenos para proyecto geotérmico Borinquen I
Terrenos para proyecto geotérmico Borinquen I
Nueva capacidad de generación geotérmica instalada Las Pailas II
Nueva capacidad de generación geotérmica instalada Las Pailas II
Subprograma II - Componente II Transmisión
Subprograma II - Componente II Transmisión
Subestación reductora Tejar adquirida
Subestación reductora Tejar adquirida
Infraestructura de Transmisión Eléctrica Liberia-Papagayo-Nuevo Colón adquirida
Infraestructura de Transmisión Eléctrica Liberia-Papagayo-Nuevo Colón adquirida
Subprograma II - Componente III Distribución y Comercialización
Subprograma II - Componente III Distribución y Comercialización
Medidores inteligentes para automatizar la lectura de consumos (AMIS), Instalados y en funcionamiento
Medidores inteligentes para automatizar la lectura de consumos (AMIS), Instalados y en funcionamiento
Medidores inteligentes para automatizar la lectura de consumos (AMIS), Instalados y en funcionamiento
Medidores inteligentes para automatizar la lectura de consumos (AMIS), Instalados y en funcionamiento
Subprograma II. Componente I Generación
Subprograma II. Componente I Generación
Red Hidrometeorológica y Comunicaciones modernizada
Red Hidrometeorológica y Comunicaciones modernizada
XI-IATI-IADB-CR-L1049
Inter-American Development Bank
Power Sector Development Program 2012-2016 (Reventazon Hydroelectric Project)
Programa de Desarrollo Eléctrico 2012-2016 (Proyecto Hidroeléctrico Reventazón)
The objective of this operation is contributing to meet the growing electricity demand, maintaining adequate levels of quality, reliability and cost, by financing the RHP.
El objetivo de la presente operación es contribuir a atender el crecimiento de la demanda de energía eléctrica, manteniendo niveles adecuados de calidad, confiabilidad y costo, mediante el financiamiento del PHR.
Ordinary Capital
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INTER AMERICAN DEVELOPMENT BANK
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Equipo de bombeo de agua y lodos adquirido Programa de Desarrollo Eléctrico 2012-2016 (Proyecto Hidroeléctrico Reventazón), Costa Rica
24.58476, -107.38093
ENERGY
ENERGIA
4502593.84
Disbursement in second quarter of 2013
18185.54
Interest repayment in forth quarter of 2013
10502804.62
Disbursement in forth quarter of 2013
68057.93
Disbursement in second quarter of 2014
68057.93
Interest repayment in second quarter of 2014
7697838.49
Disbursement in third quarter of 2014
97391.88
Disbursement in forth quarter of 2014
97391.88
Interest repayment in forth quarter of 2014
32250828
Disbursement in forth quarter of 2014
251179.11
Disbursement in second quarter of 2015
251179.11
Interest repayment in second quarter of 2015
329824.4
Disbursement in forth quarter of 2015
329824.4
Interest repayment in forth quarter of 2015
28500000
Disbursement in forth quarter of 2015
1726721.69
Disbursement in forth quarter of 2015
11307137.03
Disbursement in forth quarter of 2015
819773.52
Disbursement in second quarter of 2016
819773.52
Interest repayment in second quarter of 2016
10000000
Disbursement in third quarter of 2016
975141.93
Disbursement in forth quarter of 2016
975141.93
Interest repayment in forth quarter of 2016
10000000
Disbursement in forth quarter of 2016
11000000
Disbursement in first quarter of 2017
1221010.1
Disbursement in second quarter of 2017
1221010.1
Interest repayment in second quarter of 2017
12500000
Disbursement in second quarter of 2017
1540347.79
Disbursement in forth quarter of 2017
1540347.79
Interest repayment in forth quarter of 2017
575001210.72
Loan repayment in forth quarter of 2017
10000000
Disbursement in forth quarter of 2017
2528000
Disbursement in first quarter of 2018
183401.47
Disbursement in second quarter of 2018
183401.47
Interest repayment in second quarter of 2018
2690743.79
Interest repayment in second quarter of 2018
3922139.23
Loan repayment in second quarter of 2018
2690743.79
Interest repayment in second quarter of 2018
9700000
Disbursement in second quarter of 2018
331317.68
Disbursement in forth quarter of 2018
5478002.38
Interest repayment in forth quarter of 2018
4111562.29
Loan repayment in forth quarter of 2018
424096.62
Disbursement in second quarter of 2019
5264799.01
Interest repayment in second quarter of 2019
4017249.44
Loan repayment in second quarter of 2019
3856004.11
Disbursement in second quarter of 2019
12000000
Disbursement in second quarter of 2019
559071.7
Disbursement in forth quarter of 2019
5493202.72
Interest repayment in forth quarter of 2019
4597163.36
Loan repayment in forth quarter of 2019
35000000
Disbursement in forth quarter of 2019
1019369.46
Disbursement in second quarter of 2020
1019369.46
Interest repayment in second quarter of 2020
4086446.73
Loan repayment in second quarter of 2020
5147284.69
Interest repayment in second quarter of 2020
3594508.87
Loan repayment in second quarter of 2020
5800000
Disbursement in second quarter of 2020
23308088.63
Disbursement in third quarter of 2020
5216510.85
Interest repayment in forth quarter of 2020
6320207.76
Loan repayment in forth quarter of 2020
4971343.49
Interest repayment in second quarter of 2021
6267030.63
Loan repayment in second quarter of 2021
4894366.71
Interest repayment in forth quarter of 2021
6170770.73
Loan repayment in forth quarter of 2021
5198977.17
Interest repayment in second quarter of 2022
5876911.16
Loan repayment in second quarter of 2022
10286321.75
Interest repayment in forth quarter of 2022
12200565.1
Loan repayment in forth quarter of 2022
5820923.81
Interest repayment in second quarter of 2023
7173143.32
Loan repayment in second quarter of 2023
5623324.67
Interest repayment in forth quarter of 2023
7196677.95
Loan repayment in forth quarter of 2023
CR-L1049 First period Jan-Jun 2017-Public Report.pdf
CR-L1049 Second period Jan-Dec 2013-Public Report [40173276].PDF
Contrato Modificatorio No 2 - Programa de Desarrollo Eléctrico 2012-2016.pdf
Contrato - Programa de Desarrollo Eléctrico 2012-2016 (Proyecto Hidroelétrico Reventazón - PHR).pdf
CR-L1049 First period Jan-Jun 2015-Public Report [40181903].PDF
Contrato Modificatorio No_1 - Programa de Desarrollo Eléctrico 2012-2016 (Proyecto Hidroeléctrico Reventazón y o [39664814].PDF
CR-L1049 First period Jan-Jun 2019-Public Report.pdf
CR-L1049 Second period Jan-Dec 2014-Public Report [40178706].PDF
Informe de Terminación de Proyecto.pdf
CR-L1049 First period Jan-Jun 2014-Public Report [40176143].PDF
CR-L1049 First period Jan-Jun 2020 - Public Report.pdf
CR-L1049 Second period Jan-Dec 2018-Public Report.pdf
CR-L1049 Second period Jan-Dec 2017-Public Report.pdf
CR-L1049 Second period Jan-Dec 2015-Public Report [40363583].PDF
CR-L1049 Second period Jan-Dec 2019-Public Report.pdf
CR-L1049 First period Jan-Jun 2016-Public Report [40797363].PDF
CR-L1049 First period Jan-Jun 2018-Public Report.pdf
CR-L1049 Second period Jan-Dec 2016-Public Report.pdf
SUBPROGRAMA 2 COMPONENTE DISTRIBUCION Y COMERCIALIZACION
SUBPROGRAMA 2 COMPONENTE DISTRIBUCION Y COMERCIALIZACION
Expansión de la red de distribución: Sistemas fotovoltaicos para comunidades aisladas, instalados y en funcionamiento.
Expansión de la red de distribución: Sistemas fotovoltaicos para comunidades aisladas, instalados y en funcionamiento.
Expansión de la red de distribución: Sistemas fotovoltaicos para comunidades aisladas, instalados y en funcionamiento.
Expansión de la red de distribución: Sistemas fotovoltaicos para comunidades aisladas, instalados y en funcionamiento.
Refuerzo de red de distribución: Maquinaria mayor y menor adquiridas y en funcionamiento.
Refuerzo de red de distribución: Maquinaria mayor y menor adquiridas y en funcionamiento.
Refuerzo de red de distribución: Maquinaria mayor y menor adquiridas y en funcionamiento.
Refuerzo de red de distribución: Maquinaria mayor y menor adquiridas y en funcionamiento.
Sostenibilidad Ambiental: Infraestructura y equipo para el manejo de residuos en funcionamiento.
Sostenibilidad Ambiental: Infraestructura y equipo para el manejo de residuos en funcionamiento.
Sostenibilidad Ambiental: Infraestructura y equipo para el manejo de residuos en funcionamiento.
Sostenibilidad Ambiental: Infraestructura y equipo para el manejo de residuos en funcionamiento.
Equipo para la optimización del proceso de lectura, conexión y desconexión de medidores, instalado y en funcionamiento.
Equipo para la optimización del proceso de lectura, conexión y desconexión de medidores, instalado y en funcionamiento.
SUBPROGRAMA 2 COMPONENTE GENERACION
SUBPROGRAMA 2 COMPONENTE GENERACION
Modernización de la unidad de generación #5 de la Planta Hidroeléctrica de "Río Macho" en funcionamiento.
Modernización de la unidad de generación #5 de la Planta Hidroeléctrica de "Río Macho" en funcionamiento.
Planta de Concreto adquirida e instalada
Planta de Concreto adquirida e instalada
Equipo de bombeo de agua y lodos adquirido
Equipo de bombeo de agua y lodos adquirido
SUBPROGRAMA 2 COMPONENTE TRANSMISION Y CONTROL
SUBPROGRAMA 2 COMPONENTE TRANSMISION Y CONTROL
Modernización del Nuevo Centro de Control de Energía (NCCE) concluída.
Modernización del Nuevo Centro de Control de Energía (NCCE) concluída.
XI-IATI-IADB-CR-L1001
Inter-American Development Bank
Tourism Program in Protected Areas
Programa de Turismo en Áreas Silvestres Protegidas
The purpose of the present project is to improve Costa Rica's conservation and biodiversity through the consolidation and development of sustainable eco-tourism in and around select protected areas that form part of the National System of Conservation Areas.
REPUBLICA DE COSTA RICA
INTER AMERICAN DEVELOPMENT BANK
Ordinary Capital
SISTEMA NACIONAL DE ÁREAS DE CONSERVACIÓN
SISTEMA NACIONAL DE ÁREAS DE CONSERVACIÓN
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
ASP con sistema de monitoreo de impacto del proyecto Programa de Turismo en Áreas Silvestres Protegidas, Costa Rica
24.58476, -107.38093
ENVIRONMENT AND NATURAL DISASTERS
MEDIO AMBIENTE Y DESASTRES NATURALE
1186000
Disbursement in forth quarter of 2012
4115.88
Interest repayment in second quarter of 2013
6954.51
Interest repayment in forth quarter of 2013
1873037.7
Disbursement in forth quarter of 2013
13213.37
Interest repayment in second quarter of 2014
17545.47
Interest repayment in forth quarter of 2014
2600000
Disbursement in forth quarter of 2014
26057.44
Interest repayment in second quarter of 2015
1000000
Disbursement in third quarter of 2015
33647.24
Interest repayment in forth quarter of 2015
1500000
Disbursement in forth quarter of 2015
3200000
Disbursement in forth quarter of 2015
90904.09
Interest repayment in second quarter of 2016
3000000
Disbursement in second quarter of 2016
125600.96
Interest repayment in forth quarter of 2016
3000000
Disbursement in forth quarter of 2016
1640962.3
Disbursement in forth quarter of 2016
186467.59
Interest repayment in second quarter of 2017
826086.96
Loan repayment in second quarter of 2017
198199.31
Interest repayment in forth quarter of 2017
826086.96
Loan repayment in forth quarter of 2017
212760.18
Interest repayment in second quarter of 2018
812999.91
Loan repayment in second quarter of 2018
267282.07
Interest repayment in forth quarter of 2018
812999.91
Loan repayment in forth quarter of 2018
277914.56
Interest repayment in second quarter of 2019
812979.91
Loan repayment in second quarter of 2019
20
Loan repayment in second quarter of 2019
246968.57
Interest repayment in forth quarter of 2019
812999.91
Loan repayment in forth quarter of 2019
195659.35
Interest repayment in second quarter of 2020
812999.91
Loan repayment in second quarter of 2020
103666.82
Interest repayment in forth quarter of 2020
812999.91
Loan repayment in forth quarter of 2020
73197.62
Interest repayment in first quarter of 2021
812999.91
Loan repayment in first quarter of 2021
68347.68
Interest repayment in forth quarter of 2021
812999.91
Loan repayment in forth quarter of 2021
66139.88
Interest repayment in second quarter of 2022
812999.91
Loan repayment in second quarter of 2022
142935.64
Interest repayment in forth quarter of 2022
812999.91
Loan repayment in forth quarter of 2022
243176.43
Interest repayment in first quarter of 2023
812999.91
Loan repayment in first quarter of 2023
264179.32
Interest repayment in forth quarter of 2023
812999.91
Loan repayment in forth quarter of 2023
CR-L1001 First period Jan-Jun 2014-Public Report [40176158].PDF
Rapport pour Publication_PMR-_CR-L1001-2012-2º-Período [37873799].PDF
Relatório para publicação_PMR-_CR-L1001-2012-1º-Período [37352017].PDF
Report for Publication_PMR-_CR-L1001-2013-1º-Period [38267342].PDF
Rapport pour Publication_PMR-_CR-L1001-2011-1º-Período [36624505].PDF
Relatório para publicação_PMR-_CR-L1001-2012-2º-Período [37873131].PDF
Relatório para publicação_PMR-_CR-L1001-2011-1º-Período [36623917].PDF
Contrato Modificatorio - Programa de Turismo en Áreas Silvestres Protegidas [39660575].PDF
CR-L1001 Second period Jan-Dec 2014-Public Report [40178707].PDF
Informe para Publicación_PMR-_CR-L1001-2010-2º-Periodo [36312640].PDF
Relatório para publicação_PMR-_CR-L1001-2011-2º-Período [36915781].PDF
Informe para Publicación_PMR-_CR-L1001-2012-1º-Periodo [37353337].PDF
CR-L1001 Second period Jan-Dec 2016-Public Report.pdf
Report for Publication_PMR-_CR-L1001-2011-2º-Period [36927233].PDF
Informe para Publicación_PMR-_CR-L1001-2013-1º-Periodo [38266667].PDF
Programa de Turismo en Areas Silvestres Protegidas [880775].PDF
Report for Publication_PMR-_CR-L1001-2010-2º-Period [36313212].PDF
CR-L1001 First period Jan-Jun 2017-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1001-2010-2º-Período [36312053].PDF
Report for Publication_PMR-_CR-L1001-2011-1º-Period [36625622].PDF
Protected Areas Tourism Program [880778].PDF
CR-L1001 [39923787].PDF
Contrato - Programa de Turismo en Áreas Silvestres Protegidas.pdf
Contrato Modificatorio No 1 - Programa de Turismo en Áreas Silvestres Protegidas.pdf
Rapport pour Publication_PMR-_CR-L1001-2013-1º-Período [38266006].PDF
CR-L1001 First period Jan-Jun 2016-Public Report [40797352].PDF
INFORME PCR CR L1001 PARA PUBLICACIÓN.pdf
Rapport pour Publication_PMR-_CR-L1001-2011-2º-Período [36921994].PDF
Report for Publication_PMR-_CR-L1001-2012-1º-Period [37353996].PDF
CR-L1001 First period Jan-Jun 2015-Public Report [40181894].PDF
Informe para Publicación_PMR-_CR-L1001-2011-1º-Periodo [36625058].PDF
Informe para Publicación_PMR-_CR-L1001-2011-2º-Periodo [36924583].PDF
CR-L1001 [39746959].PDF
CR-L1001 Second period Jan-Dec 2013-Public Report [40173278].PDF
Rapport pour Publication_PMR-_CR-L1001-2012-1º-Período [37352668].PDF
Relatório para publicação_PMR-_CR-L1001-2010-2º-Período [36310160].PDF
I. Inversiones para el desarrollo turístico sostenible
I. Inversiones para el desarrollo turístico sostenible
Obras de Infraestructura turística fuera de las ASP rehabilitadas o desarrolladas
Obras de Infraestructura turística fuera de las ASP rehabilitadas o desarrolladas
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
Obras de Infraestructura turística fuera de las ASP rehabilitadas o desarrolladas
Obras de Infraestructura turística fuera de las ASP rehabilitadas o desarrolladas
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
Obras de infraestructura turística dentro de las ASP desarrolladas o rehabilitadas.
II. Fortalecimiento de la planificación y gestión sostenible del turismo
II. Fortalecimiento de la planificación y gestión sostenible del turismo
Material educativo de turismo en ASP producido y divulgado
Material educativo de turismo en ASP producido y divulgado
Iniciativas de inversión y negocios identificadas
Iniciativas de inversión y negocios identificadas
Planes y procesos de gestión de las ASP desarrollados
Planes y procesos de gestión de las ASP desarrollados
ASP con sistema de monitoreo de impacto del proyecto
ASP con sistema de monitoreo de impacto del proyecto
Guías turísticos capacitados y acreditados
Guías turísticos capacitados y acreditados
Actores del sector privado capacitados en turismo sostenible
Actores del sector privado capacitados en turismo sostenible
Municipios con Instrumentos de mejoramiento ambiental en operación
Municipios con Instrumentos de mejoramiento ambiental en operación
Planes y procesos de gestión de las ASP desarrollados
Planes y procesos de gestión de las ASP desarrollados
III. Fortalecimiento Institucional del SINAC
III. Fortalecimiento Institucional del SINAC
Conformado equipo de turismo sostenible
Conformado equipo de turismo sostenible
Plataforma electrónica de comunicación disponible
Plataforma electrónica de comunicación disponible
ASPs equipadas para la gestión del turismo
ASPs equipadas para la gestión del turismo
Plan estratégico diseñado
Plan estratégico diseñado
Publicaciones de promoción turística para ASP realizadas
Publicaciones de promoción turística para ASP realizadas
Personal del SINAC capacitado en turismo sostenible
Personal del SINAC capacitado en turismo sostenible
XI-IATI-IADB-CR-L1135
Inter-American Development Bank
Tropical Storm Nate Emergency Response Program
Programa de emergencia en respuesta a la tormenta tropical Nate
The program's objective is to restore a portion of the road infrastructure and basic water supply services damaged by Tropical Storm Nate and the floods it caused. This is expected to support the transition process of the affected population (paragraph 5.4) towards resumption of its regular
economic and social activities and to reestablish the level of access to basic public services.
El objetivo del programa es restaurar parte de la infraestructura vial y servicios básicos de agua potable afectados por la Tormenta Tropical Nate y las inundaciones por esta provocadas. Con ello se espera apoyar el proceso de transición de la población afectada (¶5.4) hacia la recuperación de sus actividades sociales y económicas regulares, y restablecer el nivel de acceso a la provisión de servicios públicos básicos.
REPUBLICA DE COSTA RICA
Ordinary Capital
COMISION NACIONAL DE EMERGENCIA
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Km de la red vial afectados por la Tormenta Nate en condiciones de operación regularizada Programa de emergencia en respuesta a la tormenta tropical Nate, Costa Rica
24.58476, -107.38093
ENVIRONMENT AND NATURAL DISASTERS
MEDIO AMBIENTE Y DESASTRES NATURALE
10996645
Disbursement in forth quarter of 2018
7106401
Disbursement in forth quarter of 2018
64893.35
Interest repayment in first quarter of 2019
1896954
Disbursement in first quarter of 2019
379069.32
Interest repayment in third quarter of 2019
306448.17
Interest repayment in first quarter of 2020
235398.91
Interest repayment in third quarter of 2020
107072.65
Interest repayment in first quarter of 2021
125216.44
Interest repayment in third quarter of 2021
120328.77
Interest repayment in first quarter of 2022
163805.96
Interest repayment in third quarter of 2022
448772.03
Interest repayment in first quarter of 2023
616920.67
Interest repayment in third quarter of 2023
677769.45
Interest repayment in first quarter of 2024
512820.51
Loan repayment in first quarter of 2024
CR-L1135 First period Jan-Jun 2018-Public Report.pdf
Programa de Emergencia en Respuesta a la Tormenta Tropical Nate - LP Público - CR-L1135.pdf
Programa de Emergencia en Respuesta a la Tormenta Tropical Nate - LP Completo Público - CR-L1135.pdf
CR-L1135 Second period Jan-Dec 2018-Public Report.pdf
Tropical Storm Nate Emergency Response Program - Public LP - CR-L1135.pdf
CR-L1135 Second period Jan-Dec 2017-Public Report.pdf
Contrato - Programa de Emergencia en Respuesta a la Tormenta Tropical Nate.pdf
CR-L1135 PCR Aprobado junio 2020.pdf
Infraestructura Vial
Infraestructura Vial
Metros de puentes afectados por la Tormenta Nate en condiciones de operación regularizada
Metros de puentes afectados por la Tormenta Nate en condiciones de operación regularizada
Km de la red vial afectados por la Tormenta Nate en condiciones de operación regularizada
Km de la red vial afectados por la Tormenta Nate en condiciones de operación regularizada
Infraestructura de provisión de agua potable
Infraestructura de provisión de agua potable
Número de sistemas de agua potable reparados que estuvieron inoperantes como consecuencia de la tormenta
Número de sistemas de agua potable reparados que estuvieron inoperantes como consecuencia de la tormenta
XI-IATI-IADB-CR-L1009
Inter-American Development Bank
First Electric Power Sector Development Program 2008-2011
Primer Programa de Desarrollo Sector Eléctrico 2008-2011
The objective is to supply the rising demand for electricity, maintaining a reasonably priced power supply at adquate quality and reliability standards, furthering and supporting Costa rica's economic growth and competitiveness and enhance societal wellbeing.
El objetivo del programa es apoyar las inversiones en el sector eléctrico en las diferentes áreas necesarias para mantener la calidad y confiabilidad del servicio, ampliar la cobertura y mejorar la generación de electricidad.
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INSTITUTO COSTARRICENSE DE ELECTRICIDAD
INTER AMERICAN DEVELOPMENT BANK
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Equipos MER en funcionamiento. Primer Programa de Desarrollo Sector Eléctrico 2008-2011, Costa Rica
9.86861, -84.04476
ENERGY
ENERGIA
10250000
Disbursement in forth quarter of 2010
1014427.28
Disbursement in forth quarter of 2010
4500000
Disbursement in forth quarter of 2010
89840.01
Disbursement in second quarter of 2011
89840.01
Interest repayment in second quarter of 2011
3037786.92
Disbursement in second quarter of 2011
9456220.61
Disbursement in third quarter of 2011
24998417.22
Disbursement in forth quarter of 2011
126503.44
Disbursement in forth quarter of 2011
126503.44
Interest repayment in forth quarter of 2011
12529112.22
Disbursement in forth quarter of 2011
14046068.69
Disbursement in first quarter of 2012
463159.4
Disbursement in second quarter of 2012
463159.4
Interest repayment in second quarter of 2012
27733293.28
Disbursement in third quarter of 2012
493901.98
Disbursement in forth quarter of 2012
493901.98
Interest repayment in forth quarter of 2012
22818899.5
Disbursement in forth quarter of 2012
732417.97
Disbursement in second quarter of 2013
732417.97
Interest repayment in second quarter of 2013
16000000
Disbursement in second quarter of 2013
9510801.84
Disbursement in third quarter of 2013
872919.04
Disbursement in forth quarter of 2013
872919.04
Interest repayment in forth quarter of 2013
20284048.7
Disbursement in forth quarter of 2013
1005358.44
Disbursement in second quarter of 2014
1005358.44
Interest repayment in second quarter of 2014
10000000
Disbursement in second quarter of 2014
5000000
Disbursement in forth quarter of 2014
1082840.56
Disbursement in forth quarter of 2014
1082840.56
Interest repayment in forth quarter of 2014
4874079.41
Loan repayment in forth quarter of 2014
14502000
Disbursement in forth quarter of 2014
1500000
Disbursement in forth quarter of 2014
10000000
Disbursement in second quarter of 2015
1171077.17
Disbursement in second quarter of 2015
1171077.17
Interest repayment in second quarter of 2015
5312152.25
Loan repayment in second quarter of 2015
8000000
Disbursement in third quarter of 2015
1321103.43
Disbursement in forth quarter of 2015
1321103.43
Interest repayment in forth quarter of 2015
5816654.28
Loan repayment in forth quarter of 2015
6126770.94
Disbursement in second quarter of 2016
8451175.15
Disbursement in second quarter of 2016
2881856.21
Disbursement in second quarter of 2016
2211378.98
Interest repayment in second quarter of 2016
6017948.18
Loan repayment in second quarter of 2016
230.91
Interest repayment in forth quarter of 2016
2185050.04
Interest repayment in forth quarter of 2016
6332985.52
Loan repayment in forth quarter of 2016
2295011.9
Interest repayment in second quarter of 2017
6332523.7
Loan repayment in second quarter of 2017
2440057.16
Interest repayment in forth quarter of 2017
6332754.61
Loan repayment in forth quarter of 2017
50000000
Loan repayment in second quarter of 2018
3112352.29
Interest repayment in second quarter of 2018
6339551.36
Loan repayment in second quarter of 2018
6868996.97
Interest repayment in forth quarter of 2018
7854949.68
Loan repayment in forth quarter of 2018
3208671.02
Loan repayment in forth quarter of 2018
4459687.19
Interest repayment in second quarter of 2019
6279763.51
Loan repayment in second quarter of 2019
4079363.59
Interest repayment in forth quarter of 2019
6311288.73
Loan repayment in forth quarter of 2019
3625351.33
Interest repayment in second quarter of 2020
2757015.19
Loan repayment in second quarter of 2020
1937078.35
Interest repayment in second quarter of 2020
4817603.09
Loan repayment in second quarter of 2020
2321902.24
Interest repayment in forth quarter of 2020
6234777.29
Loan repayment in forth quarter of 2020
2240638.7
Interest repayment in second quarter of 2021
6207671.67
Loan repayment in second quarter of 2021
465272.23
Interest repayment in forth quarter of 2021
.01
Loan repayment in forth quarter of 2021
4761174.55
Interest repayment in forth quarter of 2021
12134128.11
Loan repayment in forth quarter of 2021
5918227.66
Interest repayment in second quarter of 2022
11480732.91
Loan repayment in second quarter of 2022
3206352.58
Interest repayment in forth quarter of 2022
6336061.35
Loan repayment in forth quarter of 2022
3386295.11
Interest repayment in second quarter of 2023
7170401.21
Loan repayment in second quarter of 2023
3360233.36
Interest repayment in forth quarter of 2023
7256833.64
Loan repayment in forth quarter of 2023
Report for Publication_PMR-_CR-L1009-2012-1º-Period [37353997].PDF
Relatório para publicação_PMR-_CR-L1009-2012-2º-Período [37873132].PDF
CR-L1009 [36263994].PDF
CR-L1009 First period Jan-Jun 2015-Public Report [40181895].PDF
CR-L1009 First period Jan-Jun 2014-Public Report [40176155].PDF
Rapport pour Publication_PMR-_CR-L1009-2013-1º-Período [38266007].PDF
ADQUISICIÓN DE EQUIPO DE TOPOGRAFÍA H (power) [35345921].PDF
Relatório para publicação_PMR-_CR-L1009-2012-1º-Período [37352018].PDF
Relatório para publicação_PMR-_CR-L1009-2011-1º-Período [36623918].PDF
CR-L1009 [36280136].PDF
Rapport pour Publication_PMR-_CR-L1009-2012-2º-Período [37873800].PDF
ADQUISICIÓN DE EQUIPOS DE MEDICIÓN, COMUNICACIÓN TRANSFORMADORES DE INSTRUMENTOS, CABLE DE CONTROL, Y TABLEROS [35347161].DOCX
Report for Publication_PMR-_CR-L1009-2013-1º-Period [38267343].PDF
Report for Publication_PMR-_CR-L1009-2011-1º-Period [36625623].PDF
Informe para Publicación_PMR-_CR-L1009-2012-1º-Periodo [37353339].PDF
Informe para Publicación_PMR-_CR-L1009-2010-2º-Periodo [36312641].PDF
Rapport pour Publication_PMR-_CR-L1009-2011-1º-Período [36624506].PDF
Informe para Publicación_PMR-_CR-L1009-2013-1º-Periodo [38266668].PDF
MÁQUINAS PERFORADORAS [35361870].PDF
CR-L1009 Second period Jan-Dec 2014-Public Report [40178721].PDF
ADQUISICIÓN DE EQUIPOS DE MEDICIÓN, COMUNICACIÓN TRANSFORMADORES DE INSTRUMENTOS, CABLE DE CONTROL, Y TABLEROS K [35338119].PDF
ADQUISICIÓN DE ESTACIONES PARA EL MONITOREO DE VIENTO [35818918].PDF
Rapport pour Publication_PMR-_CR-L1009-2011-2º-Período [36921999].PDF
Report for Publication_PMR-_CR-L1009-2011-2º-Period [36927239].PDF
CR-L1009 Second period Jan-Dec 2013-Public Report [40173243].PDF
CR-L1009 Second period Jan-Dec 2015-Public Report [40363568].PDF
Relatório para publicação_PMR-_CR-L1009-2010-2º-Período [36310161].PDF
Relatório para publicação_PMR-_CR-L1009-2011-2º-Período [36915786].PDF
Rapport pour Publication_PMR-_CR-L1009-2010-2º-Período [36312054].PDF
DISEÑO Y PLANOS CONSTRUCTIVOS DEL CONJUNTO DE EDIFICIOS PARA EL NUEVO CENTRO DE CONTROL DE ENERGÍA DEL ICE Ener [35338264].PDF
Relatório para publicação_PMR-_CR-L1009-2013-1º-Período [38265349].PDF
Report for Publication_PMR-_CR-L1009-2012-2º-Period [37875234].PDF
CR-L1009A [36280139].PDF
SCADA_EMS PARA EL CENTRO DE CONTROL DE ENERGÍA Power [36207803].PDF
Report for Publication_PMR-_CR-L1009-2010-2º-Period [36313214].PDF
ADQUISICIÓN DE COMPRESORES Power [35532164].PDF
Rapport pour Publication_PMR-_CR-L1009-2012-1º-Período [37352669].PDF
CR-L1009 First period Jan-Jun 2016-Public Report [40797353].PDF
CR-L1009 [36334367].PDF
Contrato - Primer Programa de Desarrollo Eléctrico 2008-2011.pdf
Informe para Publicación_PMR-_CR-L1009-2012-2º-Periodo [37874454].PDF
ADQUISICIÓN DE PERFORADORA AUTO-TRANSPORTABLE Y SUS PERIFÉRICOS [35589474].PDF
Informe para Publicación_PMR-_CR-L1009-2011-1º-Periodo [36625059].PDF
Informe para Publicación_PMR-_CR-L1009-2011-2º-Periodo [36924588].PDF
DISEÑO, CONSTRUCCIÓN Y PUESTA EN MARCHA DE SUBESTACIÓN DE TRANSMISIÓN H (power) [35292069].PDF
Componente 1. Generación
Componente 1. Generación
Modernización de las unidades de generación #3 y #4 Planta Hidroeléctrica de Río Macho fabricadas y en sl sitio.
Modernización de las unidades de generación #3 y #4 Planta Hidroeléctrica de Río Macho fabricadas y en sl sitio.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Funcionamiento de dragas para la recuperación de embalses.
Funcionamiento de dragas para la recuperación de embalses.
Funcionamiento de dragas para la recuperación de embalses.
Funcionamiento de dragas para la recuperación de embalses.
Estudios de inversión preliminares en fuentes renovables completados.
Estudios de inversión preliminares en fuentes renovables completados.
Modernización de las unidades de generación #1 y #2 Planta Hidroeléctrica de Río Macho en funcionamiento.
Modernización de las unidades de generación #1 y #2 Planta Hidroeléctrica de Río Macho en funcionamiento.
Componente 2. Transmisión y Control
Componente 2. Transmisión y Control
Equipos MER en funcionamiento.
Equipos MER en funcionamiento.
Respaldo de transformadores.
Respaldo de transformadores.
Subestaciones "Coronado", "Jacó", "Coyol" y "Río Macho" en funcionamiento.
Subestaciones "Coronado", "Jacó", "Coyol" y "Río Macho" en funcionamiento.
Equipos MER en funcionamiento.
Equipos MER en funcionamiento.
Modernización del Nuevo Centro de Control de Energía (NCCE) Primera Fase concluída.
Modernización del Nuevo Centro de Control de Energía (NCCE) Primera Fase concluída.
Respaldo de transformadores.
Respaldo de transformadores.
Transformadores de Medición
Transformadores de Medición
Equipos MER en funcionamiento.
Equipos MER en funcionamiento.
Respaldo de transformadores.
Respaldo de transformadores.
Subestaciones "Coronado", "Jacó", "Coyol" y "Río Macho" en funcionamiento.
Subestaciones "Coronado", "Jacó", "Coyol" y "Río Macho" en funcionamiento.
Transformadores de Medición
Transformadores de Medición
Transformadores de Medición
Transformadores de Medición
Componente 3. Distribución y Comercialización
Componente 3. Distribución y Comercialización
Refuerzo de la red de distribución.
Refuerzo de la red de distribución.
Laboratorio de Eficiencia Energética para la realización de pruebas de iluminación, refrigeración, motores eléctricos y otros instalado en funcionamiento.
Laboratorio de Eficiencia Energética para la realización de pruebas de iluminación, refrigeración, motores eléctricos y otros instalado en funcionamiento.
Refuerzo de la red de distribución.
Refuerzo de la red de distribución.
Medidores para automatizar la lectura de servicio de consumo instalados y en funcionamiento.
Medidores para automatizar la lectura de servicio de consumo instalados y en funcionamiento.
Soluciones fotovoltaicas para comunidades aisladas en funcionamiento.
Soluciones fotovoltaicas para comunidades aisladas en funcionamiento.
Refuerzo de la red de distribución.
Refuerzo de la red de distribución.
Refuerzo de la red de distribución.
Refuerzo de la red de distribución.
Soluciones fotovoltaicas para comunidades aisladas en funcionamiento.
Soluciones fotovoltaicas para comunidades aisladas en funcionamiento.
Nuevos clientes conectados a la red primaria de electrificación rural.
Nuevos clientes conectados a la red primaria de electrificación rural.
Medidores para automatizar la lectura de servicio de consumo instalados y en funcionamiento.
Medidores para automatizar la lectura de servicio de consumo instalados y en funcionamiento.
XI-IATI-IADB-CR-L1024
Inter-American Development Bank
Water and Sanitation Program
Programa de Agua Potable y Saneamiento
The improvement of the services of water supply and sanitation in terms of coverage, efficiency and quality in Costa Rica, benefiting the capital (San Jose), small municipalities and rural zones.
El mejoramiento de la cobertura, eficiencia, y calidad de los servicios de sistemas de agua potable y saneamiento en Costa Rica, beneficiando la capital, pequeñas municipalidades y zonas rurales.
Ordinary Capital
INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS
INTER AMERICAN DEVELOPMENT BANK
INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS
INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Colectores Zona Norte construidos Programa de Agua Potable y Saneamiento, Costa Rica
9.8911, -84.12703
WATER AND SANITATION
AGUA Y SANEAMIENTO
5075849.51
Disbursement in forth quarter of 2015
22780.88
Interest repayment in first quarter of 2016
51006.73
Interest repayment in third quarter of 2016
54396.31
Interest repayment in first quarter of 2017
1635673.47
Disbursement in second quarter of 2017
62867.86
Interest repayment in third quarter of 2017
2468700.06
Disbursement in forth quarter of 2017
93360.31
Interest repayment in first quarter of 2018
155797.19
Interest repayment in third quarter of 2018
163511.09
Interest repayment in first quarter of 2019
10302672.95
Disbursement in third quarter of 2019
157437.05
Interest repayment in third quarter of 2019
296019.89
Interest repayment in first quarter of 2020
541191.56
Loan repayment in first quarter of 2020
13635147.79
Disbursement in third quarter of 2020
300047.88
Interest repayment in third quarter of 2020
930767.21
Loan repayment in third quarter of 2020
338404.19
Interest repayment in first quarter of 2021
930767.21
Loan repayment in first quarter of 2021
5000000
Disbursement in second quarter of 2021
7000000
Disbursement in third quarter of 2021
365826.19
Interest repayment in third quarter of 2021
1082282.36
Loan repayment in third quarter of 2021
7500000
Disbursement in first quarter of 2022
416435.43
Interest repayment in first quarter of 2022
1535407.36
Loan repayment in first quarter of 2022
6540000
Disbursement in second quarter of 2022
748734.79
Interest repayment in third quarter of 2022
1746375.1
Loan repayment in third quarter of 2022
4300000
Disbursement in forth quarter of 2022
4616000
Disbursement in first quarter of 2023
1276317.39
Interest repayment in first quarter of 2023
1889708.44
Loan repayment in first quarter of 2023
1014647.06
Disbursement in second quarter of 2023
1250000
Disbursement in third quarter of 2023
1678687.12
Interest repayment in third quarter of 2023
2083868.68
Loan repayment in third quarter of 2023
Relatório para publicação_PMR-_CR-L1024-2010-2º-Período [36310164].PDF
Rapport pour Publication_PMR-_CR-L1024-2012-1º-Período [37352674].PDF
CR-L1024 Second period Jan-Dec 2021 - Public Report.PDF
CR-L1024 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1024 First period Jan-Jun 2016-Public Report [40797358].PDF
Informe para Publicación_PMR-_CR-L1024-2010-2º-Periodo [36312644].PDF
CR-L1024 First period Jan-Jun 2019-Public Report.pdf
CR-L1024 First period Jan-Jun 2021 - Public Report.pdf
Report for Publication_PMR-_CR-L1024-2011-2º-Period [36927245].PDF
Contrato - Programa de Agua Potable y Saneamiento [38316827].PDF
Informe para Publicación_PMR-_CR-L1024-2013-1º-Periodo [38266673].PDF
CR-L1024 First period Jan-Jun 2023 - Public Report.PDF
CR-L1024 Second period Jan-Dec 2014-Public Report [40178689].PDF
Relatório para publicação_PMR-_CR-L1024-2012-2º-Período [37873135].PDF
CR-L1024 Second period Jan-Dec 2015-Public Report [40363575].PDF
Report for Publication_PMR-_CR-L1024-2011-1º-Period [36625626].PDF
Report for Publication_PMR-_CR-L1024-2013-1º-Period [38267347].PDF
Report for Publication_PMR-_CR-L1024-2012-1º-Period [37354000].PDF
CR-L1024 First period Jan-Jun 2018-Public Report.pdf
Relatório para publicação_PMR-_CR-L1024-2011-2º-Período [36915793].PDF
Informe para Publicación_PMR-_CR-L1024-2012-1º-Periodo [37353342].PDF
Contrato de Garantia - Programa de Agua Potable y Saneamiento [38316876].PDF
CR-L1024 Second period Jan-Dec 2020 - Public Report.pdf
Relatório para publicação_PMR-_CR-L1024-2011-1º-Período [36623923].PDF
CR-L1024 First period Jan-Jun 2017-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1024-2010-2º-Período [36312057].PDF
Relatório para publicação_PMR-_CR-L1024-2012-1º-Período [37352022].PDF
CR-L1024 First period Jan-Jun 2015-Public Report [40181897].PDF
CR-L1024 Second period Jan-Dec 2019-Public Report.pdf
Report for Publication_PMR-_CR-L1024-2010-2º-Period [36313218].PDF
CR-L1024 Second period Jan-Dec 2017-Public Report.pdf
Informe para Publicación_PMR-_CR-L1024-2011-1º-Periodo [36625063].PDF
CR-L1024 [39430764].PDF
CR-L1024 First period Jan-Jun 2020 - Public Report.pdf
CR-L1024 Second period Jan-Dec 2018-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1024-2013-1º-Período [38266010].PDF
Contrato Modificatorio No_ 1 - Programa de Agua Potable y Saneamiento [39543108].PDF
Informe para Publicación_PMR-_CR-L1024-2011-2º-Periodo [36924595].PDF
CR-L1024 Second period Jan-Dec 2013-Public Report [40173257].PDF
Rapport pour Publication_PMR-_CR-L1024-2011-1º-Período [36624509].PDF
Rapport pour Publication_PMR-_CR-L1024-2012-2º-Período [37873803].PDF
CR-L1024 [39744713].PDF
CR-L1024 First period Jan-Jun 2022 - Public Report.PDF
CR-L1024 Second period Jan-Dec 2016-Public Report.pdf
CR-L1024 First period Jan-Jun 2014-Public Report [40176174].PDF
Rapport pour Publication_PMR-_CR-L1024-2011-2º-Período [36922006].PDF
Agua potable en zonas periurbanas del Área Metropolitana de San José
Agua potable en zonas periurbanas del Área Metropolitana de San José
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Estudios de pre inversión elaborados
Estudios de pre inversión elaborados
Terrenos adquiridos
Terrenos adquiridos
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Diseños de obras finales elaborados
Diseños de obras finales elaborados
Agua potable en áreas rurales prioritarias
Agua potable en áreas rurales prioritarias
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Estudios elaborados
Estudios elaborados
Sistemas domiciliares de agua potable rehabilitados y ampliados
Sistemas domiciliares de agua potable rehabilitados y ampliados
Estudios elaborados
Estudios elaborados
Diseños de obras elaborados
Diseños de obras elaborados
Estudios elaborados
Estudios elaborados
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Mejoramiento ambiental del Área Metropolitana de San José
Mejoramiento ambiental del Área Metropolitana de San José
Túnel construido
Túnel construido
Colectores Zona Norte rehabilitados
Colectores Zona Norte rehabilitados
Planta de tratamiento de aguas residuales diseñada, construida y puesta en operación
Planta de tratamiento de aguas residuales diseñada, construida y puesta en operación
Servidumbres constituidas
Servidumbres constituidas
Túnel construido
Túnel construido
Redes de alcantarillado Zona Sur rehabilitadas
Redes de alcantarillado Zona Sur rehabilitadas
Redes de alcantarillado Zona Sur construidas
Redes de alcantarillado Zona Sur construidas
Servidumbres constituidas
Servidumbres constituidas
Redes de alcantarillado Zona Sur rehabilitadas
Redes de alcantarillado Zona Sur rehabilitadas
Servidumbres constituidas
Servidumbres constituidas
Emisario terrestre construido
Emisario terrestre construido
Colectores Zona Norte rehabilitados
Colectores Zona Norte rehabilitados
Colectores Zona Norte rehabilitados
Colectores Zona Norte rehabilitados
Redes de Alcantarillado Zona Norte rehabilitadas
Redes de Alcantarillado Zona Norte rehabilitadas
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Sur construidas
Redes de alcantarillado Zona Sur construidas
Colectores Zona Norte construidos
Colectores Zona Norte construidos
Colectores Zona Sur construidos
Colectores Zona Sur construidos
Redes de alcantarillado Zona Sur rehabilitadas
Redes de alcantarillado Zona Sur rehabilitadas
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Redes de alcantarillado Zona Sur construidas
Redes de alcantarillado Zona Sur construidas
Colectores Zona Sur construidos
Colectores Zona Sur construidos
Redes de Alcantarillado Zona Norte rehabilitadas
Redes de Alcantarillado Zona Norte rehabilitadas
Colectores Zona Norte rehabilitados
Colectores Zona Norte rehabilitados
Colectores Zona Norte construidos
Colectores Zona Norte construidos
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Norte construidas
Servidumbres constituidas
Servidumbres constituidas
Redes de alcantarillado Zona Sur construidas
Redes de alcantarillado Zona Sur construidas
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Sur rehabilitadas
Redes de alcantarillado Zona Sur rehabilitadas
Emisario terrestre construido
Emisario terrestre construido
Redes de Alcantarillado Zona Norte rehabilitadas
Redes de Alcantarillado Zona Norte rehabilitadas
Servidumbres constituidas
Servidumbres constituidas
Redes de alcantarillado Zona Norte construidas
Redes de alcantarillado Zona Norte construidas
Colectores Zona Sur rehabilitados
Colectores Zona Sur rehabilitados
Estudios de pre inversión elaborados (diagnosticos y factibilidad del sistema de recolección)
Estudios de pre inversión elaborados (diagnosticos y factibilidad del sistema de recolección)
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
Servidumbres constituidas
Servidumbres constituidas
Colectores Zona Sur construidos
Colectores Zona Sur construidos
Colectores Zona Norte construidos
Colectores Zona Norte construidos
Diseño de la rehabilitación y ampliación del Sistema de Alcantarillado Sanitario del AMSJ elaborado.
Diseño de la rehabilitación y ampliación del Sistema de Alcantarillado Sanitario del AMSJ elaborado.
Informes de asesoría en supervisión elaborados
Informes de asesoría en supervisión elaborados
XI-IATI-IADB-CR-L1142
Inter-American Development Bank
Towards a Green Economy: Support for Costa Rica’s Decarbonization Plan
Hacia una Economia Verde: Apoyo al Plan de Descarbonizacion de Costa Rica
The project's general objective is to support the country's progressive transition to net zerogreenhouse gas (GHG) emissions by 2050, benefiting the entire population, through reforms to: (i) strengthen management andmonitoring of climate action in Costa Rica; (ii) conserve and restore ecosystems with high rates of GHG sequestration andreplace GHG-emitting agricultural practices with GHG-sequestering ones; and (iii) incentivize the use of electric power. Thenecessary policy reforms to implement the National Decarbonization Plan will be supported under these subsectors.This is the first loan in a series of two consecutive single-tranche operations that are technically related to one another butcontractually independent and financed as programmatic policy-based loans.
El objetivo general del proyecto es contribuir a la progresiva transición del país haciacero emisiones netas de Gases Efecto Invernadero (GEI) al 2050, beneficiando a toda la población a través de reformaspara: (i) el fortalecimiento de la gestión y monitoreo de la acción climática en CR; (ii) la conservación y restauración deecosistemas de alta captación de GEI y la sustitución de prácticas agropecuarias emisoras por fijadoras de GEI; y (iii) laincentivación del uso de la energía eléctrica. Bajo estos subsectores se apoyarán las reformas de política necesarias parala implementación del Plan Nacional de Descarbonización (PD).La presente operación de préstamo es la primera de una serie de dos operaciones consecutivas de un solo desembolso,independientes contractualmente, pero vinculadas técnicamente, bajo la modalidad de préstamo Programático Basado enPolíticas (PBP)
Ordinary Capital
MINISTERIO DE HACIENDA
INTER AMERICAN DEVELOPMENT BANK
REPUBLICA DE COSTA RICA
REPUBLICA DE COSTA RICA
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
ENVIRONMENT AND NATURAL DISASTERS
MEDIO AMBIENTE Y DESASTRES NATURALE
230000000
Disbursement in second quarter of 2020
1582098.37
Interest repayment in forth quarter of 2020
1408741.12
Interest repayment in second quarter of 2021
1369224.66
Interest repayment in forth quarter of 2021
1464375.34
Interest repayment in second quarter of 2022
4124057.38
Interest repayment in forth quarter of 2022
6689098.86
Interest repayment in second quarter of 2023
7640863.67
Interest repayment in forth quarter of 2023
Programa Hacia una Economía Verde - Apoyo al Plan de Descarbonización de Costa Rica.pdf
Costa Rica. Loan proposal for the project “Towards a Green Economy. Support for Costa Rica’s Decarbonization Plan” CR-L1142.pdf
XI-IATI-IADB-CR-L1145
Inter-American Development Bank
Fiscal Sustainability Support Program II
Programa de Apoyo a la Sostenibilidad Fiscal II
The objective of this operation is to strengthen fiscal sustainability by controlling expenditure and modernizing the tax system. The specific objectives are: (i) improving the effectiveness of the macrofiscal institutional framework; (ii) increasing the efficiency of tax system management; and (iii) improving efficiency in public expenditure management (employment, administrative reform, and judicial pensions). This is the second of two operations under the programmatic policy-based loan modality.
El objetivo es fortalecer la sostenibilidad fiscal por medio del control del gasto y la modernización del sistema tributario. Los objetivos específicos son: (i) mejorar la efectividad del marco institucional macrofiscal; (ii) aumentar la eficiencia en la gestión del sistema tributario; y (iii) mejorar la eficiencia en la gestión del gasto público (empleo, reforma administrativa y pensiones judiciales). La presente operación corresponde a la segunda de dos operaciones bajo la modalidad de Préstamo Programático de Apoyo a Reformas de Política (PBP).
Ordinary Capital
REPUBLICA DE COSTA RICA
MINISTERIO DE HACIENDA
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Decreto de creación CFI aprobado. Programa de Apoyo a la Sostenibilidad Fiscal II, Costa Rica
24.58476, -107.38093
REFORM / MODERNIZATION OF THE STATE
REFORMA/MODERNIZACIÓN DEL ESTADO
250000000
Disbursement in first quarter of 2022
1250547.95
Interest repayment in second quarter of 2022
4708688.94
Interest repayment in forth quarter of 2022
7642766.99
Interest repayment in second quarter of 2023
16836836.36
Interest repayment in forth quarter of 2023
Programa de Apoyo a la Sostenibilidad Fiscal ll.pdf
CR-L1145 Second period Jan-Dec 2021 - Public Report.PDF
Costa Rica. Loan proposal for the _Fiscal Sustainability Support Program II”.pdf
Costa Rica. Propuesta de préstamo para el _Programa de Apoyo a la Sostenibilidad Fiscal II”.pdf
CR-L1145 First period Jan-Jun 2021 - Public Report.pdf
Fiscal Sustainability Support Program II.pdf
XI-IATI-IADB-CR-L1023
Inter-American Development Bank
Cantonal Road Network Program
Programa Red Vial Cantonal
To improve the accessibility of the rural population to public, social and civil and economic services, providing permanent availability and accessibility by improving rural roads. Towards this, the operation supports road decentralization, through the development of technical and institutional capabilities of local governments in charge of the cantonal network. The specific objective is to provide a better integration and connectivity to the rural population, and reduce the users' transport costs and travel time, through rehabilitation and maintenance investments, and actions directed towards the improvement of the road management and transport systems.
Mejorar la accesibilidad de la población rural a servicios públicos, sociales, cívicos y económicos, brindando transitabilidad y accesibilidad permanentes mediante la mejora de la vialidad cantonal. Para ello, apoya la descentralización vial, mediante el desarrollo de las capacidades técnicas e institucionales de los gobiernos locales a cargo de la red vial cantonal. El objetivo específico supone proveer una mejor integración y conectividad a la población rural y reducir los costos de transporte y tiempos de viaje a los usuarios a través de inversiones en rehabilitación y mantenimiento periódico, y acciones dirigidas a la mejora del sistema de gestión vial y de transporte.
Ordinary Capital
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
INTER AMERICAN DEVELOPMENT BANK
REPUBLICA DE COSTA RICA
REPUBLICA DE COSTA RICA
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
TRANSPORT
TRANSPORTE
12000000
Disbursement in forth quarter of 2011
8687.73
Disbursement in first quarter of 2012
1454.84
Disbursement in first quarter of 2012
42908.91
Interest repayment in second quarter of 2012
65534.29
Interest repayment in forth quarter of 2012
65208.67
Interest repayment in second quarter of 2013
70366.03
Interest repayment in forth quarter of 2013
68791.24
Interest repayment in second quarter of 2014
68827.4
Interest repayment in forth quarter of 2014
3000000
Disbursement in forth quarter of 2014
78116.72
Interest repayment in second quarter of 2015
5478625.27
Disbursement in third quarter of 2015
106333.66
Interest repayment in forth quarter of 2015
5378742.46
Disbursement in forth quarter of 2015
219245.62
Interest repayment in second quarter of 2016
6469236.49
Disbursement in second quarter of 2016
1588.56
Disbursement in third quarter of 2016
277161.72
Interest repayment in forth quarter of 2016
11999001.91
Disbursement in forth quarter of 2016
405519.53
Interest repayment in second quarter of 2017
1136594.74
Loan repayment in second quarter of 2017
10068404.35
Disbursement in second quarter of 2017
3867306.99
Disbursement in third quarter of 2017
548564.5
Interest repayment in forth quarter of 2017
1401552.74
Loan repayment in forth quarter of 2017
312.85
Interest repayment in first quarter of 2018
683683.7
Interest repayment in second quarter of 2018
1444239.87
Loan repayment in second quarter of 2018
846287.32
Interest repayment in forth quarter of 2018
1427611.61
Loan repayment in forth quarter of 2018
899058.79
Interest repayment in second quarter of 2019
1427583.24
Loan repayment in second quarter of 2019
819311.28
Interest repayment in forth quarter of 2019
1427622.65
Loan repayment in forth quarter of 2019
667309.38
Interest repayment in second quarter of 2020
1427602.65
Loan repayment in second quarter of 2020
364500.51
Interest repayment in forth quarter of 2020
1427602.65
Loan repayment in forth quarter of 2020
265827.37
Interest repayment in first quarter of 2021
1427602.65
Loan repayment in first quarter of 2021
257754.64
Interest repayment in forth quarter of 2021
1427602.65
Loan repayment in forth quarter of 2021
259309.75
Interest repayment in second quarter of 2022
1427602.65
Loan repayment in second quarter of 2022
585917.86
Interest repayment in forth quarter of 2022
1427602.65
Loan repayment in forth quarter of 2022
1048352.82
Interest repayment in first quarter of 2023
1427602.65
Loan repayment in first quarter of 2023
1207818.1
Interest repayment in forth quarter of 2023
1427602.65
Loan repayment in forth quarter of 2023
Contrato Modificatorio - Primer Programa para la Red Vial Cantonal [39661932].PDF
Relatório para publicação_PMR-_CR-L1023-2012-1º-Período [37352021].PDF
CR-L1023 Second period Jan-Dec 2016-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1023-2011-2º-Período [36922005].PDF
Informe para Publicación_PMR-_CR-L1023-2013-1º-Periodo [38266672].PDF
Report for Publication_PMR-_CR-L1023-2011-2º-Period [36927244].PDF
Rapport pour Publication_PMR-_CR-L1023-2010-2º-Período [36312056].PDF
Relatório para publicação_PMR-_CR-L1023-2010-2º-Período [36310163].PDF
CR-L1023 [39726758].PDF
BR-L1284 [39707183].PDF
Rapport pour Publication_PMR-_CR-L1023-2012-1º-Período [37352673].PDF
CR-L1023 Second period Jan-Dec 2017-Public Report.pdf
Relatório para publicação_PMR-_CR-L1023-2013-1º-Período [38265351].PDF
Rapport pour Publication_PMR-_CR-L1023-2011-1º-Período [36624508].PDF
Informe para Publicación_PMR-_CR-L1023-2011-1º-Periodo [36625062].PDF
COSTA RICA_ Porposal for a loan of the Cantonal Road Network Program_ Second Operation CR-L1023 (PIC) [1880245].PDF
Informe para Publicación_PMR-_CR-L1023-2010-2º-Periodo [36312643].PDF
COSTA RICA_ Propuesta de Préstamo para el programa Red Vial Cantonal_ Segunda Operación CR-L1023 (PIC) [1880244].PDF
Informe para Publicación_PMR-_CR-L1023-2011-2º-Periodo [36924594].PDF
Report for Publication_PMR-_CR-L1023-2011-1º-Period [36625625].PDF
CR-L1023 [39080831].PDF
Informe para Publicación_PMR-_CR-L1023-2012-1º-Periodo [37353341].PDF
Report for Publication_PMR-_CR-L1023-2012-1º-Period [37353999].PDF
Relatório para publicação_PMR-_CR-L1023-2011-1º-Período [36623921].PDF
CR-L1023 First period Jan-Jun 2017-Public Report.pdf
Report for Publication_PMR-_CR-L1023-2013-1º-Period [38267346].PDF
Rapport pour Publication_PMR-_CR-L1023-2013-1º-Período [38266009].PDF
Relatório para publicação_PMR-_CR-L1023-2011-2º-Período [36915792].PDF
Report for Publication_PMR-_CR-L1023-2010-2º-Period [36313217].PDF
Relatório para publicação_PMR-_CR-L1023-2012-2º-Período [37873134].PDF
CR-L1023 [39707151].PDF
Rapport pour Publication_PMR-_CR-L1023-2012-2º-Período [37873802].PDF
PCR Programa de Red Vial Cantonal.pdf
XI-IATI-IADB-CR-L1066
Inter-American Development Bank
Border Integration Program of Costa Rica
Programa de Integración Fronteriza de Costa Rica
The objective of the program is to strengthen Costa Rica¿s competitiveness by modernizing its border infrastructure, equipment, and systems, with a view to ensuring the efficient and effective coordination of the control activities performed by the border control agencies. The specific objectives are to: (i) implement a physical and regulatory system of effective control tools and processes; and (ii) provide Costa Rica¿s border crossings with the appropriate infrastructure and equipment to effectively implement control tools and processes for cargo and people. This objective is consistent with efforts under way by the countries of Central America to consolidate their regional integration process
El objetivo del programa es fortalecer la competitividad de Costa Rica mediante la modernización de la infraestructura, el equipamiento y sus sistemas fronterizos, buscando garantizar la coordinación eficiente y eficaz de los controles por parte de las instituciones con responsabilidad sobre los mismos. Los objetivos específicos son: (i) implantar un sistema físico y normativo, de procesos y herramientas de control efectivos; y (ii) dotar a los pasos de frontera de Costa Rica con la infraestructura y el equipamiento adecuado para responder efectivamente a los procesos y herramientas de control de cargas y personas. Este objetivo es consistente con los esfuerzos que realizan los países de Centroamérica para la consolidación de su proceso de integración regional.
REPUBLICA DE COSTA RICA
Ordinary Capital
INTER AMERICAN DEVELOPMENT BANK
MINISTERIO DE HACIENDA
MINISTERIO DE HACIENDA
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
6 Productos para Ventanilla Única de Comercio Exterior (VUCE), ampliada tecnológicamente, desarrollados y funcionando Programa de Integración Fronteriza de Costa Rica, Costa Rica
24.58476, -107.38093
REGIONAL INTEGRATION
INTEGRACIÓN REGIONAL
434000.0
414000.0
394000.0
375000.0
357000.0
340000.0
323000.0
308000.0
292000.0
5413581.4
500000
Disbursement in first quarter of 2019
3210.41
Interest repayment in second quarter of 2019
4645797.18
Disbursement in forth quarter of 2019
8190.13
Interest repayment in forth quarter of 2019
74402.96
Interest repayment in second quarter of 2020
32327.14
Interest repayment in forth quarter of 2020
1589188.26
Disbursement in second quarter of 2021
31517.81
Interest repayment in second quarter of 2021
40494.07
Interest repayment in forth quarter of 2021
13817712.94
Disbursement in forth quarter of 2021
119328.55
Interest repayment in second quarter of 2022
32091430.6
Disbursement in third quarter of 2022
621376.57
Interest repayment in forth quarter of 2022
1422814.3
Loan repayment in forth quarter of 2022
10720767.05
Disbursement in second quarter of 2023
1489771.62
Interest repayment in second quarter of 2023
1422814.3
Loan repayment in second quarter of 2023
27984522.57
Disbursement in forth quarter of 2023
2080297.26
Interest repayment in forth quarter of 2023
1729121.93
Loan repayment in forth quarter of 2023
PIC_ COSTA RICA_ Programa de Integración Fronteriza de Costa Rica (CR-L1066) _ Propuesta de Préstamo [39664584].PDF
CR-L1066_P595929_SP.pdf
CR-L1066_P1045710_SP.pdf
EEO_ 1_ Mapa de localización de los pasos de frontera _ LP [38245183].PDF
EEO_ 7_ Adecuación de estudios de proceso de control, gestión, infraestructura e inversión de Peñas Blancas _ LP [38241593].PDF
Contrato - Programa de Integración Fronteriza de Costa Rica.pdf
EEO_ 9_ Adecuación de estudios de proceso de control, gestión, infraestructura e inversión de Sixaola _ LP [38241658].PDF
CR-L1066_P817052_SP.pdf
CR-L1066_P504638_SP.pdf
CR-L1066_P899403_SP.pdf
CR-L1066 First period Jan-Jun 2022 - Public Report.PDF
PIC_ COSTA RICA_ Border Integration Program of Costa Rica (CR-L1066) _ Loan Proposal [39664591].PDF
EEO_ 12_ Informe legal de Peñas Blancas _ LP [38740556].docx
EEO_ 18_ Estimación de la probabilidad de sobrecostos en el proyecto _ LP [39524031].DOCX
CR-L1066_P897342_SP.pdf
CR-L1066 First period Jan-Jun 2018-Public Report.pdf
Contrato Modificatorio No. 1 - Programa de Integración Fronteriza de Costa Rica.pdf
EEO_ 11_ Análisis de procesos de ventanilla única _ LP [38740035].PDF
EEO_ 15_ Marco de Reasentamiento Involuntario (MRI) _ LP [39410570].docx
EEO_ 13_ Determinación línea base y estimación de ahorros para Peñas Blancas _ LP [38740640].docx
EEO_ 10_ Adecuación de estudios de proceso de control, gestión, infraestructura e inversión de Las Tablillas _ L [38241674].PDF
CR-L1066_P647286_SP.pdf
CR-L1066_P515402_SP.pdf
EER_ 2_ Plan de Ejecución del Programa (PEP) _ LP [38741942].PDF
CR-L1066_P500796_SP.pdf
CR-L1066 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1066_3068_SP.pdf
CR-L1066 First period Jan-Jun 2023 - Public Report.PDF
CR-L1066_P1045731_SP.pdf
CR-L1066_P731009_SP.pdf
CR-L1066 Second period Jan-Dec 2019-Public Report.pdf
EEO_ 3_ Análisis de la operación en el marco de la Política de Integración Regional _ LP [38738527].doc
CR-L1066 Second period Jan-Dec 2017-Public Report.pdf
CR-L1066_P817049_SP.pdf
CR-L1066 First period Jan-Jun 2021 - Public Report.pdf
CR-L1066_P776406_SP.pdf
CR-L1066_P776409_SP.pdf
CR-L1066_P850907_SP.pdf
EEO_ 16_ Viabilidad financiera para el Estado _ LP [38786366].docx
CR-L1066_P740761_SP.pdf
CR-L1066_P515387_SP.pdf
CR-L1066_P753067_SP.pdf
CR-L1066 Second period Jan-Dec 2021 - Public Report.PDF
EER_ 3_ Plan Operativo Anual (POA) _ LP [38724834].XLSX
CR-L1066_P741283_SP.pdf
CR-L1066_P850910_SP.pdf
CR-L1066 Second period Jan-Dec 2016-Public Report.pdf
EER_ 1_ Plan de Adquisiciones (PA) _ LP [38723705].DOCX
EEO_ 14_ Informe socioeconómico Peñas Blancas y Tablillas _ LP [38740927].docx
CR-L1066_P1062780_SP.pdf
CR-L1066 First period Jan-Jun 2015-Public Report [40181909].PDF
CR-L1066_P669681_SP.pdf
CR-L1066_P669684_SP.pdf
CR-L1066 First period Jan-Jun 2017-Public Report.pdf
CR-L1066 Second period Jan-Dec 2018-Public Report.pdf
CR-L1066 First period Jan-Jun 2020 - Public Report.pdf
EEO_ 8_ Adecuación de estudios de proceso de control, gestión, infraestructura e inversión de Paso Canoas _ LP [38241467].PDF
CR-L1066_P526795_SP.pdf
CR-L1066_P731010_SP.pdf
CR-L1066 First period Jan-Jun 2019-Public Report.pdf
CR-L1066 Second period Jan-Dec 2020 - Public Report.pdf
EER_ 5_ Informe de Gestión Ambiental y Social (IGAS) _ LP [38695023].docx
CR-L1066_P454175_SP.pdf
CR-L1066_P526790_SP.pdf
CR-L1066_4638_2_SP.pdf
CR-L1066_P1062771_SP.pdf
CR-L1066 First period Jan-Jun 2016-Public Report [40797365].PDF
2. Modernización e integración de procesos fronterizos
2. Modernización e integración de procesos fronterizos
6 Productos para Ventanilla Única de Comercio Exterior (VUCE), ampliada tecnológicamente, desarrollados y funcionando
6 Productos para Ventanilla Única de Comercio Exterior (VUCE), ampliada tecnológicamente, desarrollados y funcionando
XI-IATI-IADB-CR-L1065
Inter-American Development Bank
Cantonal Road Network II Program
Programa Red Vial Cantonal II
The program's general objective is to contribute to productivity growth and poverty reduction in Costa Rica by facilitatingcloser integration between production and consumption areas and improving the population's access to public and social services. Its specific objective isto improve the quality of the Cantonal Road Network through: (i) road rehabilitation and maintenance works that include a climate change adaptationcomponent, which will result in shorter travel times and lower operating costs; and (ii) strengthening of the institutions responsible for road networkmanagement.
el objetivo general del programa es contribuir a la mejora de la productividad y la reducciónde la pobreza en Costa Rica (CR), facilitando la integración de zonas productivas a áreas de consumo y la conexión de lapoblación a servicios públicos y sociales. El objetivo específico es la mejora de la calidad de la red de carreteras cantonales,mediante: (i) intervenciones de rehabilitación y mantenimiento incorporando adaptaciones al Cambio Climático (CC), queresultarán en reducción de tiempo de viaje y costos de operación; y (ii) el fortalecimiento de las instituciones responsables de lagestión de la red vial.
INTER AMERICAN DEVELOPMENT BANK
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
REPUBLICA DE COSTA RICA
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
Caminos cantonales rehabilitados Programa Red Vial Cantonal II, Costa Rica
24.58476, -107.38093
TRANSPORT
TRANSPORTE
1901275.2
1869587.28
1835018.64
1800450.0
1763000.64
1722670.56
1682340.48
1640570.04
1597359.24
1554148.44
1509497.28
1463405.76
1418754.6
1374103.44
1328011.92
1281920.4
1238709.6
1192618.08
1149407.28
1104756.12
1062985.68
1021215.24
979444.8
939114.72
900225.0
861335.28
825326.28
789317.28
753308.28
720180.0
687051.72
656804.16
625116.24
596309.04
567501.84
540135.0
514208.52
489722.4
465236.28
443630.88
420585.12
6760348.81
279500
Disbursement in first quarter of 2019
4389.45
Interest repayment in third quarter of 2019
1012400
Disbursement in third quarter of 2019
10158475.07
Disbursement in forth quarter of 2019
110546.66
Interest repayment in first quarter of 2020
10000000
Disbursement in second quarter of 2020
200609.95
Interest repayment in third quarter of 2020
22874109.24
Disbursement in forth quarter of 2020
164890.17
Interest repayment in first quarter of 2021
10000000
Disbursement in second quarter of 2021
309014.73
Interest repayment in third quarter of 2021
325917.14
Interest repayment in first quarter of 2022
7664808.12
Disbursement in second quarter of 2022
591568.75
Interest repayment in third quarter of 2022
1534834.8
Interest repayment in first quarter of 2023
15000000
Disbursement in second quarter of 2023
2200884.62
Interest repayment in third quarter of 2023
15000000
Disbursement in forth quarter of 2023
2852041.7
Interest repayment in first quarter of 2024
2299732.31
Loan repayment in first quarter of 2024
Obras de Mejoramiento y Rehabilitación en 10 caminos de la Red Vial Cantonal_P591105_SP.pdf
(ESR-Sys)EC-L1111_ESMR_docx [37168542].DOCX
EEO_3_Informe Viabilidad Economica_final.docx
CR-L1065_P1211152_SP.pdf
Contrato - Programa Red Vial Cantonal II.pdf
CR-L1065 First period Jan-Jun 2022 - Public Report.PDF
EER_2_Plan_de_Monitoreo_y_Evaluacion.docx
CR-L1065_P1149971_SP.pdf
CR-L1065_P989552_SP.pdf
CR-L1065_P1096506_SP.pdf
EEO_4_ Borrador de Manual de Operaciones MANOP.docx
CR-L1065 First period Jan-Jun 2023 - Public Report.PDF
CR-L1065 First period Jan-Jun 2018-Public Report.pdf
CR-L1065_P1157329_SP.pdf
CR-L1065 Second period Jan-Dec 2019-Public Report.pdf
EEO_7_Plan Nacional de Transporte 2011 - 2035.pdf
CR-L1065_P2082879_SP.pdf
CR-L1065_P724112_SP.pdf
CR-L1065 First period Jan-Jun 2020 - Public Report.pdf
CR-L1065_P1150685_SP.pdf
CR-L1065 First period Jan-Jun 2019-Public Report.pdf
CR-L1065 First period Jan-Jun 2021 - Public Report.pdf
EER_3_IGAS_CR-L1065.docx
EER_4_Plan de Adquisiciones.XLSX
CR-L1065_P1157326_SP.pdf
EEO_2_Proyectos de la Muestra Representativa.xlsx
EER_1_Plan de Ejecucion del Programa y Plan Operativo Anual.pdf
EEO_8_Analisis de Genero.docx
EEO_1_Lecciones aprendidas Programa Cantonal I.pdf
CR-L1065 Second period Jan-Dec 2021 - Public Report.PDF
CR-L1065_P591105_2_SP.pdf
EEO_5_Microempresas asociativas de mantenimiento vial (MER).pdf
CR-L1065 Second period Jan-Dec 2018-Public Report.pdf
CR-L1065_P591105_SP.pdf
EEO_6_Plan Nacional de Desarrollo 2015 - 2018.pdf
CR-L1065 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1065_P619371_SP.pdf
CR-L1065 Second period Jan-Dec 2020 - Public Report.pdf
EEO_9_Anexo Tecnico_Cambio Climatico.docx
Apoyo a las capacidades e instrumentos de gestión
Apoyo a las capacidades e instrumentos de gestión
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de funcionarios responsables de la gestión vial municipal capacitados
Número de cantones con Planes Viales Quinquenales de conservación y desarrollo elaborados
Número de cantones con Planes Viales Quinquenales de conservación y desarrollo elaborados
Rehabilitación y mantenimiento de caminos y puentes
Rehabilitación y mantenimiento de caminos y puentes
Mantenimiento rutinario por estándares realizado a través de microempresas
Mantenimiento rutinario por estándares realizado a través de microempresas
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Mantenimiento rutinario por estándares realizado a través de microempresas
Mantenimiento rutinario por estándares realizado a través de microempresas
Caminos cantonales rehabilitados
Caminos cantonales rehabilitados
Mantenimiento rutinario por estándares realizado a través de microempresas
Mantenimiento rutinario por estándares realizado a través de microempresas
Puentes construidos o rehabilitados (Incluyendo diseño adaptados a cambio climático)
Puentes construidos o rehabilitados (Incluyendo diseño adaptados a cambio climático)
XI-IATI-IADB-CR-L1081
Inter-American Development Bank
Fiscal Sustainability Support Program
Programa de Apoyo a la Sostenibilidad Fiscal
The objective of this programmatic series and the first operation is to strengthen fiscal sustainability by controlling expenditure and modernizing the tax system. The specific objectives are to: (i) improve the effectiveness of the macrofiscal institutional framework; (ii) increase the efficiency of tax system management; and (iii) improve efficiency in public expenditure management (employment, administrative reform, and judicial pensions). This is the first of two operations under the programmatic policy-based loan modality, to consist of two contractually independent and technically linked loans.
El objetivo de esta serie programática y de la primera operación es fortalecer la sostenibilidad fiscal, por medio del control del gasto y la modernización del sistema tributario. Los objetivos específicos son: (i) mejorar la efectividad del marco institucional macrofiscal; (ii) aumentar la eficiencia en la gestión del sistema tributario; y (iii) mejorar la eficiencia en la gestión del gasto público (empleo, reforma administrativa y pensiones judiciales). La presente operación corresponde a la primera de dos operaciones bajo la modalidad de Préstamo Programático de Apoyo a Reformas de Política (PBP), a conformarse de dos préstamos contractualmente independientes y técnicamente vinculados.
MINISTERIO DE HACIENDA
REPUBLICA DE COSTA RICA
INTER AMERICAN DEVELOPMENT BANK
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
REFORM / MODERNIZATION OF THE STATE
REFORMA/MODERNIZACIÓN DEL ESTADO
350000000
Disbursement in forth quarter of 2019
4109421.81
Interest repayment in first quarter of 2020
3126284.15
Interest repayment in third quarter of 2020
2065841.53
Interest repayment in first quarter of 2021
2142095.89
Interest repayment in third quarter of 2021
2158205.48
Interest repayment in first quarter of 2022
4371986.29
Interest repayment in third quarter of 2022
8951069.76
Interest repayment in first quarter of 2023
11413599.65
Interest repayment in third quarter of 2023
11709531.82
Interest repayment in first quarter of 2024
Contrato - Programa de Apoyo a la Sostenibilidad Fiscal.pdf
Carta de Política (CR-L1081).pdf
Matriz de medios de verificacion (CR-L1081).docx
Propuesta para la sostenibilidad de las finanzas públicas en Costa Rica. BID, 2018.docx
La regla fiscal de gasto corriente en Costa Rica BID, 2019.docx
Cálculo de los impactos de las reformas fiscales del lado del gasto en Costa Rica. BID 2016.docx
Plan de Monitoreo y Evaluación (CR-L1081).docx
Fiscal Sustainability Support Program (CR-L1081).pdf
XI-IATI-IADB-CR-L1137
Inter-American Development Bank
Citizen Security and Violence Prevention Program
Programa de Seguridad Ciudadana y Prevención de Violencia
The general objective of the program is to help reduce homicides and assaults in Costa Rica. The specific objectives are: (i) to improve the effectiveness of policing to prevent crime in the priority districts; and (ii) to reduce criminal behavior among adolescents and young people who are susceptible to violence in highly disadvantaged districts.
El objetivo general del proyecto es contribuir a la disminución de los homicidios y asaltos en Costa Rica. Los objetivos específicos son: (i) mejorar la efectividad policial para prevenir el delito en los distritos priorizados; y (ii) reducir los comportamientos delictivos de adolescentes y jóvenes vulnerables a la violencia, en distritos con desventajas concentradas.
MINISTERIO DE JUSTICIA Y PAZ
INTER AMERICAN DEVELOPMENT BANK
REPUBLICA DE COSTA RICA
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
P.2.3. Municipalidades y grupos de sociedad civil capacitados y utilizando las nuevas competencias adquiridas en prevención de violencia Programa de Seguridad Ciudadana y Prevención de Violencia, Costa Rica
nan
SOCIAL INVESTMENT
INVERSIONES SOCIALES
861000.0
892000.0
924000.0
955000.0
987000.0
1018000.0
1050000.0
1080000.0
1111000.0
1140000.0
1170000.0
1198000.0
1225000.0
1251000.0
1276000.0
1300000.0
1321000.0
1341000.0
1360000.0
1377000.0
1390000.0
1404000.0
1413000.0
1422000.0
1427000.0
1431000.0
1432000.0
1431000.0
1427000.0
1421000.0
1413000.0
1403000.0
1390000.0
1375000.0
1359000.0
1341000.0
1320000.0
1298000.0
1274000.0
1250000.0
1224000.0
1196000.0
1168000.0
1139000.0
1109000.0
1079000.0
1048000.0
1016000.0
985000.0
954000.0
922000.0
890000.0
860000.0
828000.0
798000.0
767000.0
738000.0
709000.0
680000.0
652000.0
625000.0
598000.0
573000.0
548000.0
523000.0
500000.0
477000.0
456000.0
434000.0
414000.0
394000.0
375000.0
357000.0
340000.0
323000.0
308000.0
292000.0
5319383.24
850000
Disbursement in forth quarter of 2021
2841.79
Interest repayment in first quarter of 2022
10617.68
Interest repayment in third quarter of 2022
5073616.76
Disbursement in forth quarter of 2022
139359.08
Interest repayment in first quarter of 2023
193168.47
Interest repayment in third quarter of 2023
12000000
Disbursement in third quarter of 2023
572956.56
Interest repayment in first quarter of 2024
Citizen Security and Violence Prevention Program CR-L1137 - Loan Proposal.pdf
CR-L1137_P1037295_SP.pdf
Contrato - Programa de Seguridad Ciudadana y Prevención de Violencia.pdf
POD - Link Criterios de Focalización Territorial.docx
CR-L1137_P844106_SP.pdf
CR-L1137_P1004363_SP.pdf
CR-L1137_P963985_SP.pdf
POD - Link Manual Operativo del Programa (Borrador).docx
CR-L1137 First period Jan-Jun 2022 - Public Report.PDF
POD - Link Presupuesto Detallado.xlsx
CR-L1137 First period Jan-Jun 2021 - Public Report.pdf
CR-L1137__P982463_SP.pdf
CR-L1137 Second period Jan-Dec 2020 - Public Report.pdf
CR-L1137 First period Jan-Jun 2020 - Public Report.pdf
CR-L1137_P987614_SP.pdf
POD - Link Diseños Técnicos Preliminares de Obras y Especificaciones Técnicas Representativa.pdf
CR-L1137_P2047188_SP.pdf
CR-L1137_P2070408_SP.pdf
CR-L1137_P2070408_2_SP.pdf
CR-L1137_P1013586_SP.pdf
CR-L1137_P1194403_SP.pdf
CR-L1137 Second period Jan-Dec 2022 - Public Report.PDF
CR-L1137_P684529_SP.pdf
CR-L1137 First period Jan-Jun 2023 - Public Report.PDF
CR-L1137_P682270_GN.pdf
CR-L1137_P2091264_SP.pdf
POD - Link Plan de Adquisiciones.xlsx
CR-L1137_P2087460_SP.pdf
CR-L1137 Second period Jan-Dec 2021 - Public Report.PDF
CR-L1137_P2070718_SP.pdf
CR-L1137_P992588_SP.pdf
CR-L1137_P2074285_SP.pdf
CR-L1137_P1150793_SP.pdf
POD - Link. Plan de Monitoreo y Evaluación.docx
CR-L1137_P2075669_SP.pdf
CR-L1137_P2070408_1_SP.pdf
4871_OC_CR Manual de Operaciones 2nda Revision.FINAL.pdf
POD - Link Análisis de Costo Beneficio del Proyecto.docx
CR-L1137_P1176079_SP.pdf
CR-L1137_P2061756_SP.pdf
CR-L1137_P917185_SP.pdf
PEP CR-L1137 Programa Seguridad Ciudadana y Prevención de la Violencia.pdf
Filtros Salvaguardas CR-L1137.pdf
CR-L1137_P2090597_SP.pdf
CR-L1137 Second period Jan-Dec 2019-Public Report.pdf
Componente 2: Prevención social de la violencia
Componente 2: Prevención social de la violencia
P.2.3. Municipalidades y grupos de sociedad civil capacitados y utilizando las nuevas competencias adquiridas en prevención de violencia
P.2.3. Municipalidades y grupos de sociedad civil capacitados y utilizando las nuevas competencias adquiridas en prevención de violencia
P.2.3. Municipalidades y grupos de sociedad civil capacitados y utilizando las nuevas competencias adquiridas en prevención de violencia
P.2.3. Municipalidades y grupos de sociedad civil capacitados y utilizando las nuevas competencias adquiridas en prevención de violencia
XI-IATI-IADB-CR-L1148
Inter-American Development Bank
Emergency Program for Fiscal Strengthening and Restoring Growth
Programa de Emergencia para el Fortalecimiento Fiscal y Restaurar el Crecimiento
The general objective of the program is to support government measures to preserve macroeconomic stability.
El objetivo general del programa es apoyar las medidas del gobierno para preservar la estabilidad macroeconómica.
REPUBLICA DE COSTA RICA
MINISTERIO DE HACIENDA
Ordinary Capital
INTER AMERICAN DEVELOPMENT BANK
INTER AMERICAN DEVELOPMENT BANK
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
REFORM / MODERNIZATION OF THE STATE
REFORMA/MODERNIZACIÓN DEL ESTADO
250000000
Disbursement in forth quarter of 2021
3341095.89
Interest repayment in second quarter of 2022
6170147.28
Interest repayment in forth quarter of 2022
9096239.21
Interest repayment in second quarter of 2023
9879876.52
Interest repayment in forth quarter of 2023
Programa de Emergencia para el Fortalecimiento Fiscal y Restaurar el Crecimiento.pdf
Costa Rica. Loan proposal for the _Emergency Program for Fiscal Strengthening and Restoring Growth”.pdf
Costa Rica. Propuesta de préstamo para el Programa de Emergencia para el Fortalecimiento Fiscal.pdf
Emergency Program for Fiscal Strengthening and Restoring Growth.pdf
XI-IATI-IADB-CR-L1022
Inter-American Development Bank
First Road Infraestructure Program
Primer Programa de Infraestructura Vial
The first specific operation will contribute to the general objective of the Conditional credit line for investment projects (CCLIP) and the content of the National Development Plan (PND) by making sustainable improvements in the level of serviceability of the national highway system (RVN).
La primera operación específica, coadyuva con el objetivo general del CCLIP y con lo previsto en el Plan Nacional de Desarrollo (PND) mediante la mejora sostenible de las condiciones del transporte de carga y pasajeros en la red vial nacional (RVN).
Ordinary Capital
REPUBLICA DE COSTA RICA
INTER AMERICAN DEVELOPMENT BANK
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
MINISTERIO DE OBRAS PUBLICAS Y TRANSPORTE
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
TRANSPORT
TRANSPORTE
3135299.07
Disbursement in forth quarter of 2010
15000000
Disbursement in forth quarter of 2010
41928.94
Interest repayment in first quarter of 2011
100186.35
Interest repayment in third quarter of 2011
48442840.98
Disbursement in forth quarter of 2011
232812.31
Interest repayment in first quarter of 2012
372255.47
Interest repayment in third quarter of 2012
9091240.65
Disbursement in forth quarter of 2012
348674.58
Interest repayment in first quarter of 2013
13033682.25
Disbursement in second quarter of 2013
500790.94
Interest repayment in third quarter of 2013
9491511.89
Disbursement in third quarter of 2013
22121570.13
Disbursement in forth quarter of 2013
4749047.39
Disbursement in forth quarter of 2013
614095.27
Interest repayment in first quarter of 2014
27112191.98
Disbursement in second quarter of 2014
807750.2
Interest repayment in third quarter of 2014
22368214.79
Disbursement in third quarter of 2014
31000000
Disbursement in forth quarter of 2014
1007939.21
Interest repayment in first quarter of 2015
20000000
Disbursement in second quarter of 2015
1274646.12
Interest repayment in third quarter of 2015
20000000
Disbursement in third quarter of 2015
41129471.78
Disbursement in forth quarter of 2015
2120729.16
Interest repayment in first quarter of 2016
7544080.81
Loan repayment in first quarter of 2016
2755564.15
Interest repayment in third quarter of 2016
7544080.81
Loan repayment in third quarter of 2016
13324929.09
Disbursement in forth quarter of 2016
2969070.74
Interest repayment in first quarter of 2017
7914217.73
Loan repayment in first quarter of 2017
2824553.95
Interest repayment in third quarter of 2017
7914197.73
Loan repayment in third quarter of 2017
20
Loan repayment in third quarter of 2017
3169277.77
Interest repayment in first quarter of 2018
7914217.73
Loan repayment in first quarter of 2018
4297708.61
Interest repayment in third quarter of 2018
7914217.73
Loan repayment in third quarter of 2018
4431840.5
Interest repayment in first quarter of 2019
7914197.73
Loan repayment in first quarter of 2019
20
Loan repayment in second quarter of 2019
4282077.62
Interest repayment in third quarter of 2019
7914217.73
Loan repayment in third quarter of 2019
3519192.39
Interest repayment in first quarter of 2020
7914217.73
Loan repayment in first quarter of 2020
2476198.71
Interest repayment in third quarter of 2020
7914217.73
Loan repayment in third quarter of 2020
853533.46
Interest repayment in first quarter of 2021
7914217.73
Loan repayment in first quarter of 2021
1388468.19
Interest repayment in third quarter of 2021
7914217.73
Loan repayment in third quarter of 2021
1211135.51
Interest repayment in first quarter of 2022
7914217.73
Loan repayment in first quarter of 2022
2024433.04
Interest repayment in third quarter of 2022
7914217.73
Loan repayment in third quarter of 2022
5228106.68
Interest repayment in first quarter of 2023
7914217.73
Loan repayment in first quarter of 2023
5804915.16
Interest repayment in third quarter of 2023
7914217.73
Loan repayment in third quarter of 2023
5921085.78
Interest repayment in first quarter of 2024
7914217.73
Loan repayment in first quarter of 2024
CR-L1022 First period Jan-Jun 2017-Public Report.pdf
CR-L1022 Second period Jan-Dec 2016-Public Report.pdf
Contrato - Primer Programa de Infraestructura Vial.pdf
Contrato Modificatorio - Primer Programa de Infraestructura Vial.pdf
XI-IATI-IADB-CR-L1043
Inter-American Development Bank
Innovation and Human Capital for Competitiveness Program
Programa de Innovación y Capital Humano para la Competitividad.
The general objective of the programa is to sthrengthen the country¿s capacity to produce, identify, difuse and use knowledge aiming at achieving productivity increases and competitiveness. The specific objectives are: (i) Contribute to the increase and fit of advanced human capital in those sectors considered national priorities and; (ii) Foster business sector investments, particularly national SMEs, in innovation and technological development
El objetivo general del programa es incrementar la capacidad del país para producir, identificar, difundir y usar conocimiento con el propósito de acelerar el crecimiento de la productividad y la competitividad del país. Los objetivos específicos son: (i) Contribuir al aumento y adecuación del capital humano avanzado requerido en las áreas prioritarias y; (ii) Fomentar aumentos en la inversión empresarial, en particular PyMES nacionales, en actividades de innovación y desarrollo tecnológico
MINISTERIO DE CIENCIA Y TECNOLOGÍA
REPUBLICA DE COSTA RICA
INTER AMERICAN DEVELOPMENT BANK
Ordinary Capital
Ordinary Capital
Inter-American Development Bank
Actual start
Planned end
Planned start
Actual end
INTER-AMERICAN DEVELOPMENT BANK
Loans and Grants accounting
2026231000
FIN-ACC-LGA@IADB.ORG
Costa Rica
I.1.1 Empresas asistidas en el acceso a servicios de desarrollo empresarial, gestion de innovacion, certificaciones y normas de calidad. Programa de Innovación y Capital Humano para la Competitividad., Costa Rica
nan
SCIENCE AND TECHNOLOGY
CIENCIA Y TECNOLOGIA
8000
Disbursement in third quarter of 2014
988830.15
Disbursement in forth quarter of 2014
3140.07
Interest repayment in first quarter of 2015
5975.52
Interest repayment in third quarter of 2015
8017595.87
Disbursement in forth quarter of 2015
38492.97
Interest repayment in first quarter of 2016
89853.63
Interest repayment in third quarter of 2016
95948.96
Interest repayment in first quarter of 2017
2333026.66
Disbursement in second quarter of 2017
103473.14
Interest repayment in third quarter of 2017
134493.74
Interest repayment in first quarter of 2018
1880170.99
Disbursement in third quarter of 2018
190002.99
Interest repayment in third quarter of 2018
236775.43
Interest repayment in first quarter of 2019
1032179.55
Disbursement in third quarter of 2019
228629.59
Interest repayment in third quarter of 2019
348095.36
Loan repayment in third quarter of 2019
8000763.05
Disbursement in forth quarter of 2019
281123.81
Interest repayment in first quarter of 2020
592228.94
Loan repayment in first quarter of 2020
190304.04
Interest repayment in third quarter of 2020
592228.94
Loan repayment in third quarter of 2020
122270.02
Interest repayment in first quarter of 2021
592228.94
Loan repayment in first quarter of 2021
2000000
Disbursement in second quarter of 2021
131584.58
Interest repayment in third quarter of 2021
651052.47
Loan repayment in third quarter of 2021
7599332.01
Disbursement in third quarter of 2021
175518.59
Interest repayment in first quarter of 2022
881335.26
Loan repayment in first quarter of 2022
352101.47
Interest repayment in third quarter of 2022
881335.26
Loan repayment in third quarter of 2022
698570.3
Interest repayment in first quarter of 2023
881335.26
Loan repayment in first quarter of 2023
862189.84
Interest repayment in third quarter of 2023
881335.26
Loan repayment in third quarter of 2023
854757.12
Interest repayment in first quarter of 2024
881335.26
Loan repayment in first quarter of 2024
CR-L1043 First period Jan-Jun 2014-Public Report [40176142].PDF
Relatório para publicação_PMR-_CR-L1043-2013-1º-Período [38265354].PDF
Informe para Publicación_PMR-_CR-L1043-2013-1º-Periodo [38266675].PDF
Contrato - Programa de Innovación y Capital Humano para la Competitividad [38815732].PDF
Relatório para publicação_PMR-_CR-L1043-2012-2º-Período [37873137].PDF
PCR Version revisada - CR-L1043 Disclose.pdf
CR-L1043 Second period Jan-Dec 2014-Public Report [40178718].PDF
Report for Publication_PMR-_CR-L1043-2013-1º-Period [38267349].PDF
CR-L1043 First period Jan-Jun 2017-Public Report.pdf
CR-L1043 First period Jan-Jun 2021 - Public Report.pdf
CR-L1043 First period Jan-Jun 2015-Public Report [40181890].PDF
CR-L1043 First period Jan-Jun 2018-Public Report.pdf
Contrato Modificatorio 1 - Programa de Innovación y Capital Humano para la Competitividad.pdf
Costa Rica_ Propuesta de préstamo_Programa de Innovación y Capital Humano para la Competitividad_ [37274232].PDF
CR-L1043 Second period Jan-Dec 2016-Public Report.pdf
CR-L1043 Second period Jan-Dec 2018-Public Report.pdf
Rapport pour Publication_PMR-_CR-L1043-2012-2º-Período [37873805].PDF
CR-L1043 Second period Jan-Dec 2013-Public Report [40173285].PDF
CR-L1043 Second period Jan-Dec 2019-Public Report.pdf
Costa Rica_ Loan Proposal_ Innovation and Human Capital for Competitiveness Program_ [37274213].PDF
CR-L1043 First period Jan-Jun 2016-Public Report [40797362].PDF
CR-L1043 First period Jan-Jun 2020 - Public Report.pdf
CR-L1043 Second period Jan-Dec 2020 - Public Report.pdf
CR-L1043 Second period Jan-Dec 2017-Public Report.pdf
CR-L1043 Second period Jan-Dec 2015-Public Report [40363580].PDF
Rapport pour Publication_PMR-_CR-L1043-2013-1º-Período [38266012].PDF
CR-L1043 First period Jan-Jun 2019-Public Report.pdf
I. Inversión para la Innovación Empresarial
I. Inversión para la Innovación Empresarial
I.1.1 Empresas asistidas en el acceso a servicios de desarrollo empresarial, gestion de innovacion, certificaciones y normas de calidad.
I.1.1 Empresas asistidas en el acceso a servicios de desarrollo empresarial, gestion de innovacion, certificaciones y normas de calidad.
I.1.1 Empresas asistidas en el acceso a servicios de desarrollo empresarial, gestion de innovacion, certificaciones y normas de calidad.
I.1.1 Empresas asistidas en el acceso a servicios de desarrollo empresarial, gestion de innovacion, certificaciones y normas de calidad.
II. Capital Humano avanzado para la competitividad
II. Capital Humano avanzado para la competitividad
II.1.2 Individuos apoyados con becas para la realización de doctorados nacionales en áreas estratégicas
II.1.2 Individuos apoyados con becas para la realización de doctorados nacionales en áreas estratégicas
II.1.3 Individuos apoyados con becas para la realización de maestrías en el exterior en áreas estratégicas
II.1.3 Individuos apoyados con becas para la realización de maestrías en el exterior en áreas estratégicas
II.1.4 Individuos apoyados con becas para la realización de doctorados (PhD) en el exterior en áreas estratégicas
II.1.4 Individuos apoyados con becas para la realización de doctorados (PhD) en el exterior en áreas estratégicas
II.1.3 Individuos apoyados con becas para la realización de maestrías en el exterior en áreas estratégicas
II.1.3 Individuos apoyados con becas para la realización de maestrías en el exterior en áreas estratégicas
II.1.1 Individuos apoyados con becas para la realización de maestrías nacionales en áreas estratégicas